Definitions and Interpretation
In this regulation:
AAC means allowable annual cut;
Act means the Great Bear Rainforest (Forest Management) Act;
affected forest licence has the same meaning as in section 26 (1) [definitions for Part 4] of the Act;
GeoBC map means a map deposited in the Media Vault, GeoBC, Victoria;
TFL means tree farm licence;
TSA means timber supply area.
In an item of a table in section 8 (2) [AACs for forest licences in GBR North TSA], 12 [AACs for forest licences in GBR South TSA] or 16 [AACs for forest licences in North Island TSA]:
exempt forest licence has the same meaning as in section 26 (1) of the Act;
former TSA, in relation to a forest licence, means the TSA that was specified in the licence, as that licence read on December 31, 2016;
licence holder, in relation to a forest licence, means the person that holds the licence as of January 1, 2017.
In an item of a table referred to in subsection (1), an affected forest licence is identified by the following information:
in column 1, the licence number of the licence;
in column 2, the licence holder;
in column 3, the licence's former TSA.
Maximum AAC and Abolition of TSAs
The maximum AAC for the GBR forest management area is 2 500 000 m 3.
The following TSAs are abolished:
the North Coast TSA;
the Mid Coast TSA;
the Kingcome TSA;
the Strathcona TSA.
GBR North TSA
The land contained within the boundaries shown and described on the GeoBC map with the map name Great Bear Rainforest North Timber Supply Area and map reference number 577.3409711 G786 TSA1 2016 is designated as the GBR North TSA.
The AAC for the Crown land in the GBR North TSA is 803 000 m 3.
The AAC of 803 000 m 3 specified for the GBR North TSA is partitioned as follows:
468 600 m 3 is attributable to those areas of Crown land that
are located within the North Island Central Coast Forest District established under the Forest Act, and
are not located within the Owikeno Lake basin;
113 200 m 3 is attributable to western red cedar and yellow cedar located within the Coast Mountains Forest District established under the Forest Act.
In respect of the AAC of 803 000 m 3 specified for the GBR North TSA,
685 024 m 3 is available to the minister for the purposes of granting under agreements referred to in section 12 (1) [form of agreements] of the Forest Act, and
117 976 m 3 is available to the timber sales manager for the purposes of granting under agreements referred to in section 12 (2) of the Forest Act.
For an affected forest licence identified in the following table,
the GBR North TSA is the area in which Crown timber may be harvested under the licence, and
the AAC set out in column 4, opposite the licence's identification information in columns 1 to 3, is the AAC that may be harvested under that licence:
GBR South TSA
The land contained within the boundaries shown and described on the GeoBC map with the map name Great Bear Rainforest South Timber Supply Area and map reference number 577.3409711 G786 TSA2 2016 is designated as the GBR South TSA.
The AAC for the Crown land in the GBR South TSA is 830 500 m 3.
In respect of the AAC of 830 500 m 3 specified for the GBR South TSA,
608 445 m 3 is available to the minister for the purposes of granting under agreements referred to in section 12 (1) [form of agreements] of the Forest Act, and
222 055 m 3 is available to the timber sales manager for the purposes of granting under agreements referred to in section 12 (2) of the Forest Act.
For an affected forest licence identified in the following table,
the GBR South TSA is the area in which Crown timber may be harvested under the licence, and
the AAC set out in column 4, opposite the licence's identification information in columns 1 to 3, is the AAC that may be harvested under that licence:
North Island TSA
The land contained within the boundaries shown and described on the GeoBC map with the map name North Island Timber Supply Area and map reference number 577.3409711 G786 TSA3 2016 is designated as the North Island TSA.
The AAC for the Crown land in the North Island TSA is 1 248 100 m 3.
In respect of the AAC of 1 248 100 m 3 specified for the North Island TSA,
885 510 m 3 is available to the minister for the purposes of granting under agreements referred to in section 12 (1) [form of agreements] of the Forest Act, and
362 590 m 3 is available to the timber sales manager for the purposes of granting under agreements referred to in section 12 (2) of the Forest Act.
For an affected forest licence identified in the following table,
the North Island TSA is the area in which Crown timber may be harvested under the licence, and
the AAC set out in column 4, opposite the licence's identification information in columns 1 to 3, is the AAC that may be harvested under that licence:
The holder of an affected forest licence identified in item 7, 8, 9, 10, 11, 17 or 18 of the table in section 12 [AACs for forest licences in GBR South TSA] may also harvest Crown timber in the North Island TSA under a new forest licence if the minister enters into the new forest licence with that holder in accordance with section 29 [direct award of new forest licences] of the Act.
The AAC that may be harvested under a new forest licence referred to in subsection (1) is the AAC set out in column 2 of the following table, opposite the holder referred to in column 1 with whom the minister may enter into the new forest licence:
Pacific TSA
The AAC for the Crown land in the Pacific TSA is
62 400 m 3 for the GBR part of the TSA, and
1 279 700 m 3 for the non-GBR part of the TSA.
In respect of the AAC of 62 400 m 3 specified for the GBR part of the Pacific TSA,
11 052 m 3 is available to the minister for the purposes of granting under agreements referred to in section 12 (1) [form of agreements] of the Forest Act, and
51 348 m 3 is available to the timber sales manager for the purposes of granting under agreements referred to in section 12 (2) of the Forest Act.
In respect of the AAC of 1 279 700 m 3 specified for the non-GBR part of the Pacific TSA,
9 999 m 3 is available to the minister for the purposes of granting under agreements referred to in section 12 (1) [form of agreements] of the Forest Act, and
1 269 701 m 3 is available to the timber sales manager for the purposes of granting under agreements referred to in section 12 (2) of the Forest Act.
TFL 25
The AAC for the TFL area for TFL 25 is 234 300 m 3.
The AAC of 234 300 m 3 specified for the TFL area for TFL 25 is allocated as follows:
152 300 m 3 is allocated to the north part of that TFL area;
82 000 m 3 is allocated to the south part of that TFL area.
TFL 39
AAC for TFL Area for TFL 39
The AAC for the TFL area for TFL 39 is
41 300 m 3 for the GBR part of the TFL area, and
1 375 000 m 3 for the non-GBR part of the TFL area.
In this section, management plan means a management plan within the meaning of section 35.2 [management plan for tree farm licence] of the Forest Act.
The AAC of 1 375 000 m 3 specified for the non-GBR part of the TFL area for TFL 39 is partitioned in order to attribute 1 203 000 m 3 to those areas of Crown land and private land that are identified as conventional harvesting areas in the map attached to the management plan for the TFL area, as that management plan read on January 1, 2017.
Adaption of Cut Control for TFL 39
In this Division:
last cut control period, in relation to a notional licence, means the cut control period that ends when the AAC adjustment period ends;
notional licence means a notional licence established by section 27 [notional division of TFL 39].
This Division applies in respect of TFL 39 in order to take into account the following:
the AAC specified by the Lieutenant Governor in Council for the GBR part of the TFL area;
the AAC specified by the Lieutenant Governor in Council for the non-GBR part of the TFL area;
if determined, the AAC determined by the chief forester for the non-GBR part of the TFL area.
During the AAC adjustment period, TFL 39 is notionally divided into
a notional licence for the GBR part of the TFL area, and
a notional licence for the non-GBR part of the TFL area.
A notional licence is deemed to be a licence as defined in section 75.4 (1) [cut control period for major licences] of the Forest Act.
The first cut control period for a notional licence is deemed to have begun on the same day as the cut control period for TFL 39, as that cut control period existed immediately before January 1, 2017.
The cut control period for a notional licence ends when the AAC adjustment period ends.
During the AAC adjustment period, the minister may assign to a notional licence the volume of timber harvested under TFL 39 or portions of that volume that the minister considers appropriate.
If there is an excess volume of timber harvested during the last cut control period for a notional licence, the excess volume
must be treated under section 75.7 [carry forward of excess harvest volume] of the Forest Act as being timber harvested during the next cut control period for TFL 39, and
must not be offset by the unharvested volume, if any, relating to the last cut control period for the other notional licence.
TFL 45
The AAC for the TFL area for TFL 45 is 114 513 m 3.
TFL 47
AAC for TFL Area for TFL 47
The AAC for the TFL area for TFL 47 is
388 500 m 3 for the GBR part of the TFL area, and
241 500 m 3 for the non-GBR part of the TFL area.
Adaption of Cut Control for TFL 47
In this Division:
last cut control period, in relation to a notional licence, means the cut control period that ends when the AAC adjustment period ends;
notional licence means a notional licence established by section 35 [notional division of TFL 47].
This Division applies in respect of TFL 47 in order to take into account the following:
the AAC specified by the Lieutenant Governor in Council for the GBR part of the TFL area;
the AAC specified by the Lieutenant Governor in Council for the non-GBR part of the TFL area;
if determined, the AAC determined by the chief forester for the non-GBR part of the TFL area.
During the AAC adjustment period, TFL 47 is notionally divided into
a notional licence for the GBR part of the TFL area, and
a notional licence for the non-GBR part of the TFL area.
A notional licence is deemed to be a licence as defined in section 75.4 (1) [cut control period for major licences] of the Forest Act.
The first cut control period for a notional licence is deemed to have begun on the same day as the cut control period for TFL 47, as that cut control period existed immediately before January 1, 2017.
The cut control period for a notional licence ends when the AAC adjustment period ends.
During the AAC adjustment period, the minister may assign to a notional licence the volume of timber harvested under TFL 47 or portions of that volume that the minister considers appropriate.
If there is an excess volume of timber harvested during the last cut control period for a notional licence, the excess volume
must be treated under section 75.7 [carry forward of excess harvest volume] of the Forest Act as being timber harvested during the next cut control period for TFL 47, and
must not be offset by the unharvested volume, if any, relating to the last cut control period for the other notional licence.