Majority
Headnote
Architect’s Certificate.—Builder’s Contract.—-Condition Precedent. —Demurrer . —Pleading. —Waiver.In contracts for the performance of work under the supervision of an architect, which, to entitle the contractor to payment for work" done, not only require its completion according to the terms of the contract, but also its approval by, and a certificate of, the architect to that effect, the performance of the work and the production of the certificate are both prerequisites to any recovery.
A formal approval and acceptance of the architect “ would not relieve the plaintiffs from their agreement to perform the work according to the plans and specifications” (Glacius v. Black, 50 N. Y. 150 ).
While the architect’s certificate is thus made essential and is otherwise indispensable to any right of recovery, its non-production may be excused when withheld by fraud or collusion, or in bad faith (Thomas v. Fleury, 26 N. Y. 26 ; Barton v. Hermann, 11 Abb. Pr. N. S. 378).
The requirement of such certificate being for the benefit and protection of the employer, he may by some definitive or expressive act, waive the necessity for its production. A mere allegation of his acceptance of the work done has no legal significance. Everything done in the progress of the work contracted for, if known to or recognized by the employer, is to be deemed accepted in part performance; and notwithstanding any such allegation as is made in the 'present case, “that the defendants duly accepted the work performed by plaintiff under and by virtue of said agreement,” the complaint presents no suggestion that the entire work as performed was accepted as a full compliance with the requirements of the contract.
Without this, no waiver of an architect’s certificate of complete compliance (so far as it gave assurance of the fact) could be deemed to be made.
This action was brought to recover a part ($550) of
The certificate of the architect being indispensable-to any recovery (so far as material), unless withheld for fraud or collusion or in bad faith, the allegation that it was so withheld “unreasonably,” has never been accepted as a justification for its non-production. Every principle upon which the architect’s determination and adjudication in this respect is-deemed operative under the contract, rejects any such “unreasonable ” action as without the consideration of the parties, or the obligations of their contract. The architect, so far as it commits any matter to his judgment, is accepted as an umpire between them (Smith v. Briggs, 3 Den. 73 ; Butler v. Tucker, 24 Wend. 449 ; Wyckoff v. Meyers, 44 N. Y. 145 ), and his mere refusal, when his impartial judgment dictates it, confers upon the contractor no right of recovery, even if, by other witnesses, he should be able to maintain that he had substantially performed the work.
The best judgment of the architect upon the matter so committed to his determination has been agreed upon as the test of the performance ; and neither party can reject or repudiate his certificate given .on the one side or his refusal to give it on the other, upon mere allegations or testimony tending to show that his action had been “unreasonable.” His entire refusal to act would throw upon the courts the duty of acting in his stead; but.until divested of the power as conferred upon him by the parties, by death, incapacity, resig
First. The mere allegation of complete performance of the work did not confer any right of action for want of the architect’s certificate.
Second. This was not supplied by the averment that the architect had “unreasonably" refused such certificate.
Third. The mere allegation that the defendants had duly accepted the work performed by plaintiff under and by virtue of said agreement added nothing in extenuation or avoidance of the necessity of such certificate, without further allegation that such work, was so accepted, not only in compliance with the contract, but was also received as a full performance "Glacius v. Black, 50 N. Y. 153 ).
The acceptance by the architect of any substitute-for that which the contract called for, if substantially variant from its terms, could not be justified (except through authority of the employer), nor can the acceptance by the employer of inferior or different work, than such as was contracted for be deemed or accredited as part or entire performance, except upon some new consideration, operating between the parties; any agreement to accept any such imperfect or incomplete work with deductions for defects agreed upon, would; be binding (Glacius v. Black, supra).
But without it, the idea that the mere declarations, of an intention or purpose to waive any right to damages already accrued is wholly unavailable as a defense thereto or as against the assertion thereof.
Under these circumstances it follows that the complaint was defective in the foregoing particulars.
The order overruling the demurrer should therefore.;
C. P. Daly, Ch. J., and J. F. Daly, J., concurred.
Cases cited
- Smith v. Brady 17 N. Y. 173 p. 45
- Thomas v. Fleury 26 N. Y. 26 p. 45, p. 46
- Bloodgood v. Ingoldsby 1 Hilt. 388 p. 45
- Bowery National Bank v. Mayor of New York 63 N. Y. 336 p. 45
- Cooney v. Winants 19 Wend. 504 p. 46
- Spear v. Downing 34 Barb. 522 p. 46
- Nellis v. De Forrest 6 How. Pr. 413 p. 46
- Hosley v. Black 28 N. Y. 438 p. 46