and true construction of the contract between them. The original agreement was dated on the 30th of Nov., 1849, and was executed by Coons only. “ In connection with and addition to” this contract, as the instrument recites, another writing was endorsed on the original contract, containing provisions different from it in reference to the payment of the expenses to be incurred in the construction of the machines, which was executed by both parties, but not under seal. The defendant gave in evidence a third instrument, signed and sealed by Coons, the plaintiff, bearing date the 17th January,. 1850, purporting to be a receipt of “ twenty-five dollars, part of fifty dollars, named as funds which were to have been paid,, .on or before the lath December last.” The receipts contained' a provision upon the part of Coons, “not to call for the' remaining $25 until after, the completion of two of said machines named in the annexed article, and • to await the directions of the defendant, as to the third, until he should conclude upon the form.” The construction of those various instruments, containing distinct stipulations in reference to the same subject, depends essentially, upon the order of time when they were executed. If the writing indorsed in the original article was, as the plaintiff insists, made subsequent to
the- 17th of January, the date of the receipt, it would annul or materially modify the stipulation of that instrument, instead of being controlled by them. This was a question of fact,, which it is to be presumed that the referee has found in favor of the plaintiff; which is accordingly approved by the Supreme-Court, in their opinion, and with which this court will not interfere. If the assumption is well founded, I can perceive-no objection to the interpretation which the Supreme Court has given to the contract, as a whole.
But the case is here presented on a bill of exceptions, and. upon the hearing before the referee, the plaintiff offered in evidence a letter from the defendant to the plaintiff, dated the-19th of October, 1849, some time prior to the agreement upon which the plaintiff had counted in his complaint. It contains directions to the plaintiff “ to use his best judgment in getting-up the machines, and to do one at a time, and as cheap as practicable, and to pay for the work when completed,” &c.