Majority
Headnote
Guaranty.—Action against acceptor.—Effect of Order for Payment and Acceptance thereof. —Assignment.—Extension of time for PERFORMANCE.—WAIVER OF FORFEITURE.—Omission of proof.— Consideration.first question which demands consideration in this case, is as to the effect and nature of the acceptance of the order or draft drawn by Lewis upon the defendant. The draft was drawn in favor of Gosson and Monohon; who had agreed to perform a certain portion of the work which Lewis had entered into a contract with the defendant to perform in the erection of certain buildings upon the land of the defendant. The order was drawn at the end of the contract of Lewis with Gosson and Monohon, for the amount to be paid to them “on the completion of the above contract when approved by me.” The counsel for the defendant claims, that the contract created by the acceptance, if valid, was collateral to an original contract on the part of Lewis ; a promise to pay the debt of another, and therefore a contract of suretyship or guaranty, and hence within the statute of frauds.
A guaranty is defined by the elementary writers to be a promise to answer for the payment of some debt oi
The case shows that the defendant had made a contract with Lewis for the erection of certain buildings upon land which the defendant owned, and which he was to convey to Lewis after the buildings were completed. The defendant making advances to him as provided in the contract, Lewis contracted with G-osson and Monohon to excavate the cellars, and build the cellar walls, and made the order for the amount of the contract upon the defendant, who accepted the same upon the conditions stated in the acceptance.
This constituted the entire arrangement, and I am unable to discover any valid ground upon which it can be claimed, that the acceptance of the defendant was a
In Van Wagner v. Terrett ( 27 Barb., 181 ), an agreement was entered into for the erection of certain buildings, and a draft was drawn by the contractor upon the defendant, who had entered into the contract with the builder, for the payment of a sum of money as per contract and to be applied on the second payment,, which draft was accepted by the defendant, and it was held that the draft was not a bill of exchange, because it was not for the payment of money absolutely, and at all events that the acceptance was not a guaranty, because the relation of the principal and surety did not exist at the time the draft was accepted, and it was not created thereby, and that the promise was an original undertaking. Of a simular import is Studwell v. Terrett ( 4 Bosw., 527 ). The cases cited are directly in point, and in principle analagous to the case at bar.
It may therefore, I think, be assumed that the defendant undertook to pay absolutely upon the completion of the contract and its approval by Lewis; his liability was not made contingent upon the failure of
As there was no guaranty, the next question to be considered is what was the effect of the order and acceptance. By the original contract between Lewis and the defendant, the latter was to pay Lewis five thous- and dollars on or before the first tier of beams were on. By the contract between Lewis and Monohon, the sum
Although the order does not specifically refer to the contract between Lewis and Nichols in terms, yet it does refer to and is made a portion of a contract of Lewis with Cosson and Monohon, and the contract between Lewis and the defendant having been introduced in evidence, it is entirely apparent that the order was to be paid from the money arising from the funds which was to be realized under the last mentioned contract. The order and acceptance related to the funds, and was an appropriation of the money which was payable by the defendant when that money was actually due. The authorities which hold that the order must specify the fund from which the money is to be paid to constitute an assignment, are cases where there was no written acceptance of the order (Watson v. The Duke of Wellington, 1 Russ. & Mylne, 602; Philips v. Stagg, 2 Edw. Ch. 188 ; Hotter v. Ellwanger, 4 Lans., 8 , 12, 13).
The order in this case having been accepted by the defendant in connection with the acceptance, I think operated per se as an assignment of the fund which the defendant might become liable to pay within Lowrey v. Steward ( 25 N. Y, 239 ); See also Parker v. City of Syracuse (31 Id., 376 ).
But whether it was an assignment or not, it was a promise to pay upon the completion of the work men
The defendant’s counsel urges several objections, upon the assumption that the contract was a contract of guaranty and not an independent contract, and as I have arrived at the conclusion that it was not a contract of guaranty, it is only necessary to examine such of them as possibly may be applicable to this aspect of the case.
1. As to the extention of the time of completion of the contract,—it was assented to by Lewis and the contractor, and the failure of the plaintiff to perform within the time limited in the contract will not prevent a recovery upon the performance after the time specified, if the delay was assented to by the defendant. There was proof to show that the defendant assented to the prosecution of the work after the time for its completion had expired; that he superintended it; was there sometimes twice a day ; and until the walls were completed he made no objection and conveyed no intimation that the delay did not meet his approval. When there is no willful departure from the terms of the contract, nor any material omission in its essential parts, and the contractor has faithfully performed it in substance, he will not be held to have forfeited his rights by reason of an unimportant or strictly technical omission. A substantia] compliance is only required, and if the owner suffers the builder to go on after the time limited has expired, without expressing his disappro
2. It is insisted that there was a failure of the condition precedent, which requires that the first tier of beams should be laid on and levelled up before any payment was to be made. The answer to this position is, that the act of the defendant prevented the laying of the first tier of beams. The walls were ready for them, and the defendant was bound to have them laid within a reasonable' time. Instead of this, defendant Lewis cancelled the contract by mutual consent on August 12, and Hichols sold the lots. The defendant thus made it impossible for this to be done, and he is estopped from insisting upon any such condition (Burtis v. Thompson, 42 N. Y., 246 ).
3. It is said that the order was never assigned or transferred to the plaintiff. I do not discover that this point was made upon the trial. If it had been, it may have been obviated by proper proof, and therefore it is not important to consider. It may be observed the order and acceptance were a part of the contract, and with the contract were delivered to the plaintiff, and, I think, passed with the assignment of the contract, which carried everything relating to it. The order and acceptance were the means of enforcing payment of the demands against the defendant, and a transfer of the contract operated according to law to assign every-' thing relating to it (See Bolen v. Crosby, 49 N. Y., 183 , 184).
The point that the acceptance of the defendant was without consideration and therefore nudum pactum is
There is no other question in the case which demands comment, and after a careful examination I am satisfied that the judgment was right, and should be affirmed.
Church, Oh. J., concurred.
Folger, Rapadlo, and Andrews, JJ., concurred in result.
Allen and Grover, JJ., absent.