Majority
Headnote
Contract — agreement "of contractor to collect and pay sub-contractor — assignment — liability of assignee on promise of assignor.-The material facts are nbt in dispute, and were established principally by documentary evidence. Both parties having moved for a direction of a verdict, and neither having asked that any issue of fact be submitted to the jury, it is practically a concession that none of the essential facts are controverted. .
In April, 1902, Rumrill & Carter, a firm of building contractors of the city of Buffalo, PT. Y., entered into a contract with the firm of C. A. Weed & Co., of the same place, for the building and erection of a store building in said city at the agreed price. of $49,300, subject to additions and deductions, the Work to be done under the direction and to the satisfaction of Green & Wicks, architects, and to be paid for upon their certificate and recommendation.
In June following,. Rumrill & Carter entered into a contract with the plaintiff, the Buffalo Glass Company, to provide all of the glass and glazing for the said building for the sum of $849. About the same time other parties niade sub-contracts with Rumrill & 'Carter for the doing of other parts, of the work. In fact,, Rumrill & Carter sublet all the work except the mason work, which they did- themselves. The plaintiff performed its contract and received its pay therefor excepting the sum -of $249.05, to recover which, with interest thereon from June 13,. 1903, this action is brought.
Shortly after securing the contract of C-A. Weed & Co., and after all the sub-contracts were made, including the plaintiff’s, the firm of Rumrill & Carter assigned its contract to the German Bank of Buffalo. When such assignment was made Mr. Rtimrill had a talk with Mr. Georger, president of the German Bank of Buffalo,
It is practically conceded that the plaintiff knew that the German Bank was receiving the funds from Weed & Co. upon the Rumrill & Carter contract. The payments by Weed & Co. to Rumrill & Carter were made to the German Bank. The money was deposited in the name of Rumrill & Carter. From time to time the sub-contractors were paid out of the German Bank funds. The moneys so paid to the sub-contractors, including the plaintiff, were paid by checks of the firm, Rumrill & Carter. Finally, trouble arose
Under these circumstances it seems to me clear that the defendant, having purchased from the receiver this contract, this lien and any and all obligations which arose under the bond and knowing all the conditions and circumstances, is liable for the amount owing to the plaintiff. It seems to me that the plain principles of equity require that the judgment in this case should be affirmed.
The defendant purchased from the receiver of the German Bank the contract between Rumrill & Carter and C. A. Weed & Co. It purchased also all right, title and interest acquired by the lien filed by Rumrill as surviving partner, and in and to the bond which was given by C. A. Weed & Co. to relieve its property from the incumbrance of such lien. The defendant knew all the conditions and circumstances attending the transfer of such' lien and the rights acquired under the action of foreclosure and under the bond, and it is apparent that one of the conditions which were understood by the defendant was that it took such asset or claim subject to the lien or claim of the plaintiff and the other sub-contractors. The evidence very conclusively shows that the defendant received as a result of the work done by the firm of Rumrill & Carter or by Rumrill, as surviving partner, the sum of $5,500, and that it was understood by all parties that such sum should be distributed to pay the claims of the sub-contractors. This the defendant refused to do and this action was brought.
There is no new or novel proposition of law involved in this case. The plaintiff contracted to do certain work for Rumrill & Carter in the carrying out of their contract with C. A. Weed & Co. Rum-rill & Carter assigned such contract to the German Bank, informing it of its obligation to the plaintiff and the other sub-contractors.
I think it clear that when the defendant purchased from the ' receiver of the German Bank the claims and obligations involved in the contract between Rumrill & Carter and, C. A. Weed & Co. it became obligated to devote whatever it might receive under such contract to the payment of the claims of the sub-contractors, and it having received from Weed & Co. sufficient for that purpose this plaintiff, as a sub-contractor, is entitled to -receive the balance of its claim. . •
Rone of the exceptions which are called to our attention by appellant constitute reversible error. As before said, the facts are undisputed. By the uncontradicted evidence the defendant obtained money from C. A. Weed & Co. for which it paid no other consideration than one dollar, and which, as I think,' ought to be applied under the circumstances in payment of the claims of plaintiff and the other sub-contractors of . Rumrill & Carter, the amount so received by the defendant being amply sufficient for that purpose.
The judgment and order appealed from should be affirmed, with costs.
All concurred.
Judgment and order affirmed, with costs.