Contract — agreement appointing plaintiff to superintend erection of building — reserved right of owner to terminate subcontracts — payment of judgment recovered by subcontractor after termination of subcontract — principal and agent — unauthorized oral agreement made by agent with subcontractor — agent liable to principal for loss caused by unauthorized or negligent acts — evidence—judicial notice — cost of union labor.This action was brought to recover a balance alleged to be due and owing to the plaintiff under and by virtue of the provisions of a contract in writing made by the parties to this action on the 1st day of March, 1904, by which the plaintiff, therein designated as the contractor, agreed to furnish and provide all materials and perform all the work necessary for the erection of an office building on premises owned by defendant, likewise designated owner, in the city of Binghamton, N. Y., according to plans, drawings and specifications to be furnished by the architects of the owner, the building to be completed on or about the 1st day of March, 1905, or within such additional time after that date as would equal the period that the contractor might be delayed by the owner in commencing the excavation after the 1st of April, 1904. The contract was construed by the parties as constituting the plaintiff superintendent of construction for defendant, notwithstanding certain general provisions designed to insure completion within the time specified, and such it was in effect, at least as between the parties, for the owner agreed to reimburse the contractor for “the total necessary actual cost of all labor and material,” and to pay it, evidently as compensation for its services, five per cent in addition thereto, it being provided that the contractor should not receive a percentage on the cost price of any material which the owner might have and which might be used in the building, but only upon the expense in laying and using the same, and that in no event should the five per cent exceed the sum of $25,000; and it was provided that the materials should be purchased pursuant to competitive bidding, and
There is no controversy with respect to the cost of the work, or the amount of plaintiff’s percentage thereon or the balance unpaid on either item. The only questions arise with respect to a claim made by the defendant to an offset against the amount claimed by the plaintiff, on account of two items of expenditure which it claims it was obliged to make, owing to acts of the plaintiff in violation of its duty under the contract.
On the 15th day of October, 1901, the plaintiff, pursuant to the provisions of the contract, let the work “ mentioned in the specifications and shown on the drawings ” for the “ Plain and Ornamental Plastering ” to McNulty Brothers, who agreed to
On the 27th day of February, 1905, McNulty Brothers filed a mechanic’s lien against the premises for $11,000.93 on the agreed price and value of the labor and materials performed and furnished by them. They brought an action in the Supreme Court in Broome county to foreclose the lien, and made the plaintiff and defendant herein parties defendant, and in their complaint alleged that they were induced to abandon their contract under an agreement by the plaintiff herein to pay them the cost and expenses of the labor and materials performed and furnished and'ten per cent in addition thereto, and alleged that the work was performed and the materials furnished with the knowledge, consent and approval of the owner. Both defendants denied the making of the agreement and pleaded the facts herein stated in justification for the termination of the contract. Qn the trial of the issues in that action the court found that an oral agreement was made as alleged between the plaintiff herein and McNulty Brothers on the 26th day of November, 1904, and that any rights the defendants or either of them had -or might have had to terminate the written contract were waived, surrendered and superseded by the oral agreement ” between McNulty Brothers and the Andrew J. Robinson Company, and that the cost of the work and materials with ten per cent added was $10,522.63, which was also the reasonable value thereof, and a foreclosure was accordingly decreed. Both defendants appealed, but the judgment foreclosing the lien was affirmed without opinion. (See 130 App.
No testimony was offered on the trial of this action. The evidence is wholly documentary and consists of the decision and judgment roll in the mechanic’s lien action, the certificates of the architects, notices from defendant to plaintiff and from plaintiff to McNulty Brothers, and of admissions contained in the pleadings and made on the trial. With respect, therefore, to the matters concerning which findings were made in the other action, neither party offered any further evidence. Counsel for plaintiff, however, concedes that plaintiff had no “ direction ” from defendant to make the oral contract with McNulty Brothers, by which it was found in the other action they were induced to surrender the work to plaintiff in an uncompleted condition. In view of that admission and of documentary evidence clearly showing that defendant in authorizing plaintiff to terminate the contract with McNulty Brothers contemplated that such termination should be had and that the work should be completed under and in accordance with the terms of the contract, it must be assumed that such oral contract was not authorized by the defendant. On the 28th of November, 1904, the defendant by letter gave plaintiff specific instructions with respect to completing the work in a manner to hold McNulty Brothers for any deficiency and, so far as appears, plaintiff assumed to acquiesce without informing defendant with respect to the oral contract made two days before. If the court in the other action considered that the defendant authorized the oral contract, then it would have held defendant liable for any deficiency judgment, but plaintiff only was so held liable. Doubtless defendant was interested in having the work speedily finished, and in taking over the work for that purpose, but it was asserting that as a matter of right under the contract. Its attitude conferred no implied authority on plaintiff to make the oral contract, and there is nothing to indicate that plaintiff ever claimed to have received authority to make the oral contract or that defendant ratified it. The learned counsel for the respondent contends that the finding in the other action with respect to the oral contract was not material
It is claimed that the ornamental plastering was not embraced in the contract with McNulty Brothers, but that it is included in the amount claimed by defendant as the cost of completing that contract. The sole basis for that claim is an assertion made on the trial by counsel for plaintiff to the effect that the ornamental plastering, although expressly specified in the contract, was not included in the specifications, to which counsel for the defendant assented by saying that he would accept the statement of counsel for the plaintiff with respect thereto. We are unable to say from an examination of the specifications, which it is recited in the contract are for plain and ornamantal plastering, whether they cover both or only the plain plaster. That is not material, however, for it was alleged in the answer and expressly admitted by the reply that the defendant “ was obliged to and did finish and complete said plastering work contracted to be done by said McNulty Bros, as aforesaid, for which it was obliged to and did pay under the direction and with the approval of the plaintiff, the sum of $11,232.11.” The architects also duly certified under the contract, with a view to
It appears that owing to labor conditions the defendant directed plaintiff, after the termination of the contract with McNulty Brothers, to complete the contract by day labor, employing only union men, and that it was so completed. The claim is made by counsel for respondent that the cost of completion in such circumstances would not have been the measure of damages against McNulty Brothers and cannot be as against plaintiff. It appears, however, that the defendant expressly required that plaintiff pay no higher rate of wages than McNulty Brothers paid, and it must be assumed that plaintiff observed this requirement. On terminating the work for cause under the contract with McNulty Brothers plaintiff was not required to relet it by contract, but was unrestricted with respect to the manner in which the work should be finished. Unless, therefore, we are able to say by judicial notice that union labor is more expensive at the same rate than non-union labor, which manifestly we cannot do, there is no basis for this contention.
We are, therefore, of opinion that the defendant should have been allowed the two offsets claimed by it, viz., $14,346.02, the amount of the McNulty Brothers judgment, which was paid on the 3d day of March, 1909, together with interest thereon to the date of the judgment, together aggregating $18,757.42, and the additional cost of completion over and above McNulty Brothers’ contract price, and five per cent thereon, and five per cent on said amount of $10,522.63, erroneously allowed to plaintiff by the judgment, and interest on these three items from the 10th day of August, 1905, which is the last date from which plaintiff was allowed interest to the date of the judgment, which three items and interest aggregate $4,596.10.
It follows, therefore, that the judgment should be modified accordingly, and as modified affirmed, without costs, and all
Ingraham, P. J., McLaughlin and Clarke, JJ., concurred; Scott, J., dissented.
Judgment modified as directed in opinion, and as modified, affirmed, without costs. • Order to be settled on notice.