Majority
Headnote
Lien—mechanic’s lien on municipal improvement — default of original contractor—liens of subcontractors measured by rights of original contractor — when suit to foreclose lien premature — cost to city of completing work yet undetermined.Present — Scott, Laughlin, Dowling, Smith and Davis, JJ.
The following is the opinion delivered at Special Term:
This is an action to foreclose a mechanic’s lien on a public improvement arising by reason of materials furnished and services performed for the contractor, Blake & Williams, under a contract with the city of New York, for installing a heating and ventilating apparatus in new public school 91, Queens. The said contract was declared abandoned by the board of education by resolution adopted at a meeting held on November 24, 1915. The contract price to complete the work under said contract was $39,972. There has been certified for payment the sum of $31,251.60. There has been actually paid the sum of $28,889.10. There is now held by the comptroller the sum of $2,362.50, which sum was certified for payment on the 15th day of October, 1915. By a resolution adopted January 12, 1916, the board of education awarded to E. Rutzler Company a contract, No.' 44,165, to complete and finish the work originally to be done by Blake & Williams under contract No. 40,831, and this contract complete is to cost the city of New York the sum of $9,175 if the work to be done thereunder is completed by E. Rutzler Company. The questions to be decided by the court in this proceeding are whether the lienors should be paid out of the sum of $2,362.50 held by the comptroller, or whether they should be restricted to the sum which is the difference between the amount unexpended ($11,082.90) and the sum it will cost to complete, which at present is estimated at the the sum of $9,175, which difference equals the sum of $1,907.90, or further, whether all sums remaining in the hands of the city,
Cases cited
- Seibert v. Dunn 216 N. Y. 237 p. 580
- Foshay v. Robinson 137 N. Y. 134 p. 581
- Herrmann & Grace v. Hillman 203 N. Y. 435 p. 581
- Fraenkel v. Friedmann 199 N. Y. 351 p. 581