Majority
Headnote
Sales — action for refusal to accept goods — contract for tin to be shipped from China in October — tender of shipment made in September not in compliance with contract — October embargo by United States government not defense, especially since contract covered that contingency?This action is to recover damages for breach of contract based on defendant’s failure to accept five tons of No. 1 Chinese tin, ninety-nine per cent pure, shipment from China, October, 1918.
The trial was had before the court without a jury by stipulation and judgment was directed for $3,526.92 in favor of the plaintiffs. Most of the facts were stipulated, and a copy of the War Trade Board’s regulations revoking all licenses to import tin from China after October 20, 1918, was received in evidence. There was only one witness called by the plaintiffs who said that he Was unable to purchase Chinese tin of the quantity ordered to be shipped from China during October, 1918, in the New York market. He said that he made no attempt to make such purchase until the 17th of October, 1918, although the time within which the goods were to have been shipped under the contract would expire the 20th of October, 1918. He also testified that the tin which was tendered to the defendant was sold in various lots to other parties at the market price on the dates of sale after defendant’s refusing to accept the September tin. No particular tin was purchased to fill this contract, but the order was filled out of tin purchased in June, 1918, before the date of the contract in suit, and at that time it was not allocated to any particular contract.
Defendant also called but one witness who was defendant’s manager, who testified that he applied to plaintiffs for the name of the steamer carrying shipments of tin, but the plaintiffs never replied to the request, nor sent in any manner the name of the steamer. This constituted the only oral evidence in the case.
The defendant’s contention is that plaintiffs having tendered tin other than that contracted for, to wit, tin shipped in September, 1918, when the contract called for shipment in October, 1918, plaintiffs cannot recover, since defendant was under no duty to ’accept any tin other than that, called for by the contract. This is the prevailing rule in a cause of this nature. When the seller sets forth that the goods will be shipped at a certain time in his contract and he ships before that time, a tender of the goods so shipped in the absence of waiver by the buyer is not a good tender and the buyer may insist upon the goods specified in the contract.
Nor did the embargo declared by the United States government on October 20,1918, give the plaintiffs the right to tender September tin in performance of th§ir agreement to deliver the October tin, especially so because the contract specifically provided for such an eventuality.
The resolution attached to the contract suspended its operation until the removal of the embargo, or in case the embargo continued for ninety days after the tin was ready for shipment, the seller was permitted to tender and the buyer to accept it at the place where it then was located.
There is also error alleged in that the damages were inadequately proven, which complaint seems borne out by the record, but for the reason that plaintiffs did not perform the conditions precedent and have thus failed to establish a cause of action, judgment dismissing the complaint should be rendered and the judgment given below reversed.
The judgment should be reversed, with costs, and the complaint dismissed, with costs.
Dowling, Meebell, Maetin and Bubb, JJ., concur.
Judgment reversed, with costs, and complaint dismissed, with costs.
Cases cited
- Hill v. Blake 97 N. Y. 216 p. 393