Majority
Headnote
Liens — mechanics’ liens — action to foreclose mechanics’ liens on dwelling houses — evidence shows that plaintiffs did not substantially perform contract — defendants, by moving into premises, did not waive defects in building — certificate of occupancy not determination that contract was performed — plaintiffs entitled to recover for extra work — defendants entitled to larger recovery on counterclaim.This appeal involves the question of whether the plaintiffs can be said to have performed substantially the contracts which they made to build two houses, one for Mr. and Mrs. Eggers
The specifications required the roofs “to be thoroughly flashed and guaranteed water proof.” The roofs of both houses leaked badly during the first rain storm, which occurred about a week after the defendants took possession. Investigation showed that the flashings had been improperly installed. Each house had to have a portion of the roof removed, flashings properly installed and the roofs, and incidentally some stucco, relaid. In addition, the specifications in connection with both houses required sheet rock ceilings to be installed in the garages. This was not done. Further, specifications called for concrete pillars under the porches and sun parlors of each house. Wooden posts were substituted. The specifications also called for brick coping on stoops and blue stone treads on cellar stairs. Instead of this, cement was substituted.
The principles of law pertaining to the question of substantial performance are clear in their application to the facts in this case. In the latest case upon the subject, namely, Jacob & Youngs, Inc., v. Kent ( 230 N. Y. 239 ), the specifications of a building contract required the plaintiff to provide wrought-iron pipe for the plumbing of the grade known as “ ‘ standard pipe ’ of Reading manufacture.” The plaintiff instead installed similar pipe known as “ Cohoes ” pipe. It appears from the opinion that the difference between the two pipes was as follows: “ Reading pipe is distinguished from Cohoes pipe and other brands only by the name of the manufacturer stamped upon it at intervals of between six and seven feet. Even the defendant’s architect, though he inspected the pipe upon arrival, failed to notice the discrepancy.” Even such a slight deviation from the specifications presented a close question as to whether the plaintiff had had the performance under his contract to which he was entitled. The Court of Appeals held that there was substantial performance, but three members of the court dissented. In the case at bar the failure to perform the contract on the part of the plaintiffs is far greater than in Jacob & Youngs, Inc., v. Kent (supra). This is so, considering alone the failure to comply with the specifications in connection with the cementing
Two other questions arise. The plaintiffs were permitted to
In the Eggers Action
For roof and stucco...................... $630 88
For electric wiring....................... 19 00
For sheet rock ceiling in garage............ 110 00
Replacing broken window glass............ 8 00
- $767 88
Amount allowed by trial court for relaying
concrete in cellar and runway........... $600 00
Allowance on account of water............ 1 60
- 601 60
Making a total of............................. $1,369 48
Deducting this amount from the total amount of extra
work performed by the plaintiffs, namely.......... 1,520 00
Leaves a balance of........................... $150 52
In the Breden Action
$593 90 For roof and stucco......................
25 75 For electric wiring.......................
55 00 For sheet rock ceiling in garage............
1 50 For replacing broken glass................
36 50 For replacing front door..................
- $712 65
Allowed on account of water.............. 2 45
- 602 45
Making a total of............................. $1,315 10
work performed by the plaintiffs, namely.......... 1,465 00
Leaves a balance of........................... $149 90
Dowling, P. J., McAvoy, Martin and O’Malley, JJ., concur.
In each case: Judgment modified as indicated in opinion, and as so modified affirmed, with costs to the appellants. Settle order on notice.
Cases cited
- Jacob & Youngs, Inc. v. Kent 230 N. Y. 239 p. 430
- Easthampton Lumber & Coal Co. v. Worthington 186 N. Y. 407 p. 431
- Cawley v. Weiner 236 N. Y. 357 at 361 p. 431