Lewis H. Saper, as Trustee in Bankruptcy of the Estate of Tangredi Contracting Corp., Appellant, v. Depot Construction Corp., Respondent.

Judgment awarded plaintiff unanimously modified to increase the amount thereof from $7,965.25 to $8,020.64 and, as so modified, affirmed, with costs to the respondent. The allowance of 10% to the defendant for its overhead is computed at $1,191.92, since the aggregate cost of completing the subcontractor’s contract was $11,919.19. Present — Dore, J. P., Callahan, Breitel, Botein and Bergan, JJ.