← Cases

In re the Arbitration between Ace Mechanical Contractors, Inc. & Gevyn Construction Corp.

11 A.D.2d 1043 Court N.Y. App. Div. Decision date 1960-10-17 English

Contents

Majority

p. 1043
In the Matter of the Arbitration between Ace Mechanical Contractors, Inc., Respondent, and Gevyn Construction Corp., Appellant.

Motion to stay arbitration proceeding pending determination of the appeal, granted upon the conditions set forth in the stipulation of the parties, dated October 7, 1960. Appellant is directed to argue or submit the appeal on December 9, 1960. The appeal is ordered on the calendar for said date. The record and appellant’s brief must be served and filed on or before November 21, 1960. Nolan, P. J., Beldoek, Ughetta, Christ and Pette, JJ., concur.