Majority
In an action to recover damages for breach of a construction contract, the plaintiff appeals from an order of the Supreme Court, Nassau County (Robbins, J.), dated February 2, 1988, which granted, after a trial pursuant to CPLR 3212 (c), the defendant’s motion for summary judgment dismissing the complaint as barred by the applicable Statute of Limitations.
Ordered that the order is affirmed, with costs.
The defendant constructed heating, ventilating and air-conditioning systems in the plaintiff’s utilities plant. On December 4, 1979, the plaintiff commenced this breach of contract action against the defendant to recover damage for defective construction. Thereafter, the defendant moved for summary judgment dismissing the complaint as time barred.
A cause of action predicated upon defective construction accrues upon completion of "actual physical work” on the construction contract (Cabrini Med. Center v Desina, 64 NY2d 1059 , 1061; Phillips Constr. Co. v City of New York, 61 NY2d 949 ; State of New York v Lundin, 60 NY2d 987 ). In this case, the key date for Statute of Limitations purposes is December 4, 1973. In accordance with a prior decision and order of this court, a trial was conducted pursuant to CPLR 3212 (c) to determine if actual physical work under the contract was completed prior to December 4, 1973 (see, County of Nassau v Sand & Co., 114 AD2d 483 ).
The admissible evidence proffered by the plaintiff did not suffice to controvert the defendant’s testimonial and documentary proof that the only work performed after December 4, 1973 was its subcontractor’s routine recalibration of temperature controls. The fact that the defendant did not certify the
Even if the recalibration of latently defective temperature controls is characterized as repair work in light of the testimony of the plaintiffs project manager that the temperature control panel never functioned "acceptably” prior to December 4, 1973, such repair work was at most incidental to the construction of the heating, ventilating and air-conditioning systems and cannot serve to extend the accrual date of the plaintiffs cause of action (see, Cabrini Med. Center v Desina, 64 NY2d 1059 , 1061, supra; Yeshiva Univ. v Fidelity & Deposit Co., 116 AD2d 49 , 53-54).
Since "by no rational process could the trier of the facts base a finding in favor of the [plaintiff] upon the evidence * * * presented” (see, Blum v Fresh Grown Preserve Corp., 292 NY 241 , 245; Lipsius v White, 91 AD2d 271 , 277), the court properly discharged the jury at the close of all the evidence upon finding, as a matter of law, that no physical work on the construction contract was completed on or after December 4, 1973. Accordingly, the court did not err in granting the defendant’s motion for summary judgment dismissing the complaint as barred by the six-year Statute of Limitations. Kunzeman, J. P., Weinstein, Rubin and Kooper, JJ., concur.
Cases cited
- Cabrini Medical Center v. Desina 64 NY2d 1059 at 1061 p. 619, p. 621
- Phillips Construction Co. v. City of New York 61 NY2d 949 at 951 p. 619, p. 621
- State v. Lundin 60 NY2d 987 p. 619, p. 621
- County of Nassau v. H. Sand & Co. 114 AD2d 483 p. 619
- Yeshiva University v. Fidelity & Deposit Co. 116 AD2d 49 at 53-54 p. 621
- Blum v. Fresh Grown Preserve Corp. 292 NY 241 at 245 p. 621
- Lipsius v. White 91 AD2d 271 at 277 p. 621