Majority
—Judgment, Supreme Court, New York County (Karla Moskowitz, J.), entered March 1, 1993, inter alia, awarding damages in favor of plaintiff and against defendant-appellant, and bringing up for review, inter alia, prior orders of the same court and Justice granting plaintiff’s motion for summary judgment in lieu of complaint “with interest as prayed for allowable by law to be computed by the Clerk”, and excusing plaintiff’s failure to settle a judgment within 60 days as required by 22 NYCRR 202.48, unanimously affirmed, with costs.
Inasmuch as plaintiff’s delay in settling the judgment was brief and its excuse reasonable, it was not an abuse of discre
Cases cited
- Garcia v. New York City Transit Authority 193 AD2d 414 p. 340
- Schwartz v. Turner Holdings, Inc. 139 AD2d 458 at 459 p. 340