Majority
In an action in the Supreme Court, Westchester County, by plaintiff, Tibbetts Contracting Corporation, a subcontractor of the defendant O & E Contracting Company, Inc. (the general contractor retained by the owner, the defendant Vioe Realty Corp.), to foreclose the plaintiff’s mechanic’s lien for $30,217 on the defendant Vice’s real property, in which the defendant O & E asserted a cross claim, against all the defendants to foreclose its own mechanic’s lien in the sum of $30,163.27; and which action was consolidated for trial with a prior action then pending in the Supreme Court, Hew York County, by the said Vioe to recover damages against the said O & B for breach of contract, in which O & E asserted two counterclaims (treated at the consolidated trial as a single counterclaim or cross complaint) to recover $60,963.54 for work, labor and materials furnished under the contract and $2,750.73 damages for Vice’s alleged wrongful termination of the contract, the said defendant Vioe appeals from a judgment of the said Supreme Court, Westchester County, rendered June 10, 1963 upon the court’s decision and opinion after a nonjury trial (see H. Y. L. J., May 2, 1963, p. 17, col, 6), and thereafter amended by order dated July 25,1963, which inter alia,', (a) awarded $49,000, plus interest of $12,250 and costs of $130, totaling $61,380, to the defendant O & B upon its cross complaint against said defendant Vioe; (b) awarded $30,217, plus interest of $6,647.74 and costs of $251,80, totaling $37,116.54, to the plaintiff Tibbetts against both said defendants O & B and Vioe; and (c) decreed foreclosure of the plaintiff Tibbetts’ mechanic’s lien, with provision for a deficiency judgment against the defendant Vioe in favor of the said plaintiff and the defendant O & B. At the trial, O & B was permitted to assert, in the Westchester County action, its counterclaim for money damages, and to withdraw its cross claim for foreclosure of its lien. At the conclusion of the trial, the court denied a motion by the plaintiff Tibbetts to amend its complaint so as to add a cause of action directly against the defendant Vioe to recover $30,217 damages for breach of contract, nevertheless, as indicated above, the judgment: (a) is in favor of the plaintiff Tibbetts against both said defendants for said amount (plus interest and costs); (b) is in favor of the defendant O & E against defendant Vioe for $49,000 plus interest and costs; and (c) grants plaintiff foreclosure of its lien together with a deficiency judgment against defendant Vioe. Hone of the parties to the appeal here has questioned or complained as to the form of said judgment. By express provision, the judgment is stated to have been
Cases cited
- Van Clief v. Van Vechten 130 N. Y. 571 at 577 p. 916
- Brainard v. County of Kings 155 N. Y. 538 at 544 p. 916
- Grombach Productions, Inc. v. Waring 293 N. Y. 609 at 615 p. 916
- Miller v. Schloss 218 N. Y. 400 at 406—408 p. 916
- Oursler v. Armstrong 10 N Y 2d 385 p. 916