Majority
Order unanimously affirmed with costs. Memorandum: Supreme Court properly denied the motion of third-party plaintiff, Dallas Homes, Inc. (Dallas), for partial summary judgment against third-party defendant, J & P Custom Masonry (J & P). Dallas, the general contractor on a residential construction project, seeks common-law indemnification from J & P, its masonry subcontractor, for liability imposed upon Dallas under Labor Law § 240 (1) as the result of injuries sustained by Charles W. Brutcher (plaintiff), a J & P employee. Dallas met its initial burden on the motion by submitting proof that it did not supervise, direct or control J & P’s work (see, Hayes v Crane Hogan Structural Sys., 191 AD2d 978 ; Damon v Starkweather,
Cases cited
- Damon v. Starkweather 185 AD2d 633 p. 877
- Miller v. Wilmorite, Inc. 231 AD2d 843 p. 877
- Paterson v. Hennessy 206 AD2d 919 p. 877
- Allman v. Frank L. Ciminelli Construction Co. 184 AD2d 1022 p. 877