Majority
—-In two actions arising out of a building construction contract which were tried together before a jury, but in each of which a separate judgment of the Supreme Court, Westchester County, was entered, the owner and the contractor (who are the only parties to the actions, except for the third-party defendant in Aetion No. 1) cross-appeal as follows: 1. The owner, the above-named Board of Education, appeals: (a) as plaintiff in Aetion No. 1 and as limited by its briefs, from so much of the judgment in that aetion, entered September 8, 1965 as is against it in favor of the contractor, defendant A. Barbaresi & Son, Inc., upon the court’s decision in part dismissing the eomplaint at the close of the board’s ease as plaintiff; and (b) as defendant in Aetion No. 2, from the judgment in that aetion, entered June 1, 1965, against it in favor of A. Barbaresi & Son, Inc., as plaintiff in that aetion, upon the court’s decision made during the course of the trial (CPLR 4401). 2. The contractor, A. Barbaresi & Son, Inc., as third-party plaintiff in Action No. 1, appeals from so much of the judgment in that aetion as dismissed its third-party complaint upon the court’s decision consequent upon dismissal of the main eomplaint. Judgments reversed on the law, and a new trial granted as to all issues between the parties to both actions and the parties to the third-party aetion, with costs to abide the event. The questions of fact have not been considered. In Aetion No. 1, which sounds in negligence and breach of contract, the board sought to recover from the contractor the sums which the board allegedly was required to pay to adjacent landowners in satisfaction of claims asserted by them against the board for injury to their property by reason of the contractor’s improper performance of the work. In Action No. 2, the contractor sued to recover the balance allegedly owing to it under the contract and for extras and change orders. As to Action No. 1, the payments made by the Board of Education to the adjoining property owners, for which it seeks to hold the contractor liable, were not made without authorization. It had the power under subdivision 6 of section 50-e of the General Municipal Law
Ughetta, Acting P. J., Christ, Hill, Rabin and Benjamin, JJ., concur.
Cases cited
- Teresta v. City of New York 304 N. Y. 440 p. 856
- Cesario v. Chiapparine 21 A D 2d 272 p. 856
- Glacius v. Black 50 N. Y. 145 p. 856
- H. M. Hughes Co. v. Sapphire Realty Co. 11 N Y 2d 17 p. 856
- Condict v. Onward Construction Co. 210 N. Y. 88 p. 856