Majority
Cross appeals from a judgment of the Supreme Court (Maney, J.), entered July 15, 1999 in Albany County, upon a decision of the court in favor of plaintiff.
The principal issue presented in this litigation between plaintiff, an electrical contractor, and defendant, the owner of a
It is well settled that, in spite of the inclusion in a construction contract of “[a] clause which exculpates a contractee from liability to a contractor for damages resulting from delays in the performance of the latter’s work * * * damages may be recovered for: (1) delays caused by the contractee’s bad faith or its willful, malicious, or grossly negligent conduct, (2) uncontemplated delays, (3) delays so unreasonable that they constitute an intentional abandonment of the contract by the contractee, and (4) delays resulting from the contractee’s breach of a fundamental obligation of the contract” (Corinno Civetta Constr. Corp. v City of New York, 67 NY2d 297 , 309 [citations omitted]; see generally, Kalisch-Jarcho, Inc. v City of New York, 58 NY2d 377 , 384-385). Here, plaintiff pursued two theories at trial: that the delays were uncontemplated and largely arose from a continuing breach of duty by defendant’s construction management team, which failed to supervise and coordinate the work of the various subcontractors on the site.
Supreme Court credited the testimony of plaintiff’s president and an architectural engineer called as plaintiff’s expert witness who each detailed the causes of the delays that plagued
1 Section 6.06 of the “Terms and Conditions to Contract” provided, in pertinent part, as follows: “(a) If Contractor shall be delayed in the commencement, prosecution or completion of the Work or shall be obstructed or hindered in the orderly progress of the Work by any act, neglect or default of Owner, Construction Manager, Architect, [or] Other Contractor * * * which preclude the continuation of the Project or the Work or portion thereof in a practicable manner then the time fixed for completion of the Work shall be extended for a period equivalent to the period of the delay incurred by Contractor as determined by Owner. No extension shall be granted unless a claim in writing therefore [sic] is presented to Construction Manager within seventy-two (72) hours of the start of such delay, obstruction or hindrance. Failure to give notice as provided herein constitutes a waiver of claim by Contractor. In the event of a continuing cause of delay, only one claim is necessary. “(b) Contractor expressly agrees for itself, its Subcontractors and suppliers not to make, and hereby waives, any claim for damages on account of any delay, obstruction or hindrance. Contractor’s sole remedy for any delay, obstruction or hindrance shall be an extension of the time in which to complete the Work.”
“Notwithstanding our broad scope of review in a nonjury trial, we accord great deference to the credibility determinations rendered by the trial court due to its ability to view the witnesses and the evidence firsthand [citations omitted]” (Auger v State of New York, 263 AD2d 929 , 930; see, Matter of Rowe, 274 AD2d 87 , 92; Silverman v Mergentime Corp./J.F. White, Inc., 252 AD2d 925 , 926; Douglas Constr. v Marcais, 239 AD2d 803 ). According the fact finder the deference to which it is entitled, we find that Supreme Court reasonably credited the testimony that the project impediments were wholly unanticipated and the opinion proffered by plaintiffs expert that they were of a character and magnitude not ordinarily encountered or anticipated by parties to a contract of this nature. Moreover, as the evidence established that defendant’s construction management team failed to substantially fulfill the express contractual obligation to schedule and coordinate the work, resulting in extensive work interruptions or delays and inefficient labor deployment, we see no basis to disturb Supreme Court’s determination that there was a pervasive and ongoing breach of the contract. Under the totality of the circumstances, finding an ample basis in the record for the court’s factual conclusion that the project delays were uncontemplated and that defendant was responsible for a breach of fundamental contractual obligations, we decline to disturb the holding that the “no damages for delay” clause did not bar plaintiffs claim for money damages (see, Mid-State Precast Sys. v Corbetta Constr. Co., 202 AD2d 702 , lvs dismissed 84 NY2d 923 , 86 NY2d 855 ).
We disagree with defendant’s argument that plaintiffs request for damages should have been rejected in its entirety because the August 1995 correspondence was not sufficiently particularized to comply with the notice requirement. In contrast to the detailed contract specifications at issue in A.H.A. Gen. Constr. v New York City Hous. Auth. ( 92 NY2d 20 , 25 [notice provision required “verified detailed statements of the damages sustained together with documentary evidence of such damages”]), the case upon which defendant relies, the contract in this case required only the submission of “a claim in writing” and provided that one claim would be sufficient in the event of a continuing delay. Having previously notified defendant of its intent to file a claim for pecuniary losses due to the project delays, plaintiff detailed the continuing delays in an August 2, 1995 letter. Defendant’s contention that this correspondence failed to afford notice because it preceded the incidents which led to the delays is wholly unsupported by the record. Thus, assuming the notice requirement was applicable to plaintiffs claim, we concur with Supreme Court that plaintiff provided contractually adequate notice at least as early as August 1995, thereby justifying reimbursement for damages incurred thereafter.
Arguing that the notice provision was inapplicable because it refers to requests for extensions and not claims for money damages, plaintiff maintains that Supreme Court erred in restricting its recovery in each of the six categories of damages awarded to expenses or losses incurred after August 1995. As plaintiffs notice of appeal challenges only so much of the judgment as denied its claim for damages for extended home office
Finally, we find plaintiff’s request to recover home office overhead expenses[2] to be unavailing. In rejecting plaintiff’s argument that proof is not necessary for this item of damages, we repeat the well-established proposition that “[a] contractor wrongfully delayed by its employer must establish the extent to which its costs were increased by the improper acts because its recovery will be limited to damages actually sustained” (Berley Indus. v City of New York, 45 NY2d 683 , 687; see, Mid-State Precast Sys. v Corbetta Constr. Co., 202 AD2d 702 , 704, supra). Finding this rule applicable to damages for increased home office overhead expenses (see, Berley Indus. v City of New York, supra, at 687-688), we do not fault Supreme Court for viewing plaintiff’s evidence, which did no more than approximate such expenses by calculating a proportion of company-wide labor costs over job-specific labor costs for the relevant time period, as insufficient to establish the requisite causal link between the delays and actual increased costs (see, Novak & Co. v Facilities Dev. Corp., 116 AD2d 891 , 892).
We have considered the parties’ remaining contentions and find them to be unpersuasive.
Cardona, P. J., Peters, Carpinello and Rose, JJ., concur. Ordered that the judgment is affirmed, without costs.
2 Plaintiff has not raised any issue concerning the warehouse worker and truck expenses in its brief on appeal.
Cases cited
- Corinno Civetta Construction Corp. v. City of New York 67 NY2d 297 at 309 p. 844
- Kalisch-Jarcho, Inc. v. City of New York 58 NY2d 377 at 384-385 p. 844
- Auger v. State 263 AD2d 929 at 930 p. 845
- In re the Estate of Rowe 274 AD2d 87 at 92 p. 845
- Silverman v. Mergentime Corp. 252 AD2d 925 at 926 p. 845
- Douglas Construction, Inc. v. Marcais 239 AD2d 803 p. 845
- Mid-State Precast Systems, Inc. v. Corbetta Construction Co. 202 AD2d 702 at 704 p. 845, p. 847
- People v. Bowman 84 NY2d 923 p. 845
- A.H.A. General Construction, Inc. v. New York City Housing Authority 92 NY2d 20 at 25 p. 846
- Marocco v. Marocco 53 AD2d 707 at 708 p. 847
- Berley Industries, Inc. v. City of New York 45 NY2d 683 at 687 p. 847
- Novak & Co. v. Facilities Development Corp. 116 AD2d 891 at 892 p. 847