Majority
Judgment, Supreme Court, New York County, entered January 5,1970, reversed, on the law and the facts, and vacated, and a new trial directed, with costs and disbursements to abide the event. In this action for damage to plaintiff’s building the jury rendered a comparably small verdict against the owner of the adjacent property and more sizable verdicts against contractors who respectively did the excavating and pile driving. These verdicts were in different amounts. Under the charge of the court no differentiation was permissible. Clearly what the jury did was to find against the owner for damage to a skylight, which damage was exactly proved as to amount, and exonerated the owner for the other damage, which consisted of damage to the building through settling. As to this damage the jury apportioned it between the remaining defendants upon some unascertainable basis. While under proper instructions the jury might have corrected this error, this was not done. The general rule, where the jury has improperly apportioned damage between tort defendants, of entering judgment for the larger amount (Polsey v. Waldorf-Astoria, 216 App. Div. 86 ) would not be applicable, as the larger amount may or may not reflect what the jury meant to find was plaintiff’s damage. Instead, the court directed a flat 30% reduction in the three jury awards, including the award against the owner which was in the sum of $1,140 and accurately reflected the cost of repairing the skylight. This hardly corrected the situation. Furthermore, the error was compounded by the court submitting the text of certain sections of the Administrative Code to the jury without explanation as to the liability imposed and without directing the jury’s attention to which sections were applicable and which were not. In addition, some members of the court are of the opinion that the verdict- is against the weight of the evidence, particularly in that a substantial part of the damage to the building was shown to have existed before either of the appealing defendants undertook any work on the adjoining plot. Concur — Stevens, P. J., Murphy and Steuer, JJ.; MeGivern and Nunez, JJ., dissent in the following memorandum by Nunez, J.: The plaintiff established by clear evidence, and the jury found, that the appealing defendants failed to provide sufficient
Cases cited
- Savko v. Brooklyn & Queens Transit Corp. 166 Misc. 84 p. 555
- Dalrymple v. Williams 63 N. Y. 361 p. 555
- Toth v. Kennedy & Smith, Inc. 285 N. Y. 579 p. 555
- People v. Kingston 8 N Y 2d 384 at 387 p. 555