000. Plaintiff sought recovery upon the theory of
quantum meruit, claiming the reasonable value of the work performed until the breach to be $1,976,975, less $1,163,686 (moneys previously paid to plaintiff), resulting in a claimed net sum due of $813,289. Thus, by employing a
quantum meruit theory of recovery, plaintiff sought to gain a net surplusage over the payments due pursuant to the contract of $608,289. It is contended that the unilateral termination of the contract by the municipality permits such a windfall. I agree that the law permits plaintiff to abandon the contract and seek recovery in
quantum meruit under the circumstances here involved
(Clark v.
Mayor, etc., of City of New York, 4 N Y. 338 ). I do not read that case, however, as supporting a “ penalty ” recovery. In
Clark, the contract provided for 150,000 cubic yards of earth to be excavated at the unit price of $1 a yard. After some 68,000 yards of earth had been excavated, the governmental authority, just as in the case at bar, decided not to go forward with the remaining portion of the contract. The issue, therefore, was whether Clark was entitled to $1 per yard for the some 68,000 yards, plus whatever profit he might have made had the contract been completed so that he might he made whole in damages for the breach by the defendant, or whether he had the right to deem the contract terminated and rescinded and recover in
quantum meruit the actual reasonable value of the work completed at the time of the contract’s termination. The evidence there supported a finding that the geological character of the premises excavated was such that the reasonable value of the some 68,000 yards excavated, largely rock, was substantially more than the base unit price of $1 per yard; and the Court of Appeals held that Clark had the right to recover in
quantum meruit such actual reasonable value, rather than to rely upon the ordinary contract damages of the amount specified in the contract, less the reasonable cost of completion. The effect of this decision, therefore, was merely to decree as an elective remedy a determination of the value of the work done as against the total contract and to make plaintiff whole for the value of the work done. It is clear that such an apportionment is appropriate. A hypothetical builder who takes a contract for $50,000 to build a house and brings it to enclosure, at which point the owner decides to abandon it, certainly should have the right to recover the $50,000, less what it would have cost him to finish the job so that his profit under the job would thus be preserved to him. The proof, however, in such a situation might be onorous. The builder would have to prove what it would cost him for the plumbing and heating, the electrical work, the plastering, landscaping, utilities and equipment installations, air conditioning, decoration and whatever else had to be done for the completion of the contract, in order to arrive at the damages . due pursuant to the contract. The holding of the Court of Appeals, therefore, in
Clark was merely that such a builder is not limited to the single remedy of damages
ex contractu and that when such a breach occurs the builder has the right to elect to deem the contract at an end (the term “ recission ” being, of• course, inappropriate, as the contract has already been “terminated” by the unilateral default of the owner). In such event, the builder should be entitled to recover the fair and reasonable value of the work done. While it is clear that á tailor engaged to make a suit, or a cabinet-maker to" fashion a chair, may not impose a substantially unfinished job upon a purchaser, it is shocking to the conscience to say that if the builder of the World Trade Center cleared the ground, excavated the foundations and built a structure up to 50 stories, and circumstances made it impossible for him to go forward, the owner would then be entitled to retain several hundred- million dollars’ worth of work, making no payment therefor. Since materialmen and work