Majority
Judgment, Supreme Court, New York County, entered January 13, 1978, finding defendant liable for damages in the amount of $2,484,108.80 is reversed, on the law, vacated, and the case remanded, without costs or disbursements, for a hearing on the question of damages only. While this court affirms the liability aspect of this action, we find that damages were incorrectly assessed. The hearing will confine itself to plaintiffs out-of-pocket expenses and reasonable value of his services, less the value of the land at date of breach of contract. Concur-Evans, Markewich and Yesawich, JJ.
Plaintiff Brickman, an attorney, was engaged in the business of owning, building and operating shopping centers. Prior to 1973, defendant Woolworth had entered into two leases with the plaintiff. Under those two leases, plaintiff agreed to build shopping centers in return for the defendant’s long-term rental of a portion of the premises. In the first week of April, 1973, a representative of the defendant, named Murphy, called Brickman to inquire whether he would be interested in building a third shopping center and Woolco store in Trumbull, Connecticut. The plaintiff responded in the affirmative. On April 3, 1973, Murphy wrote a letter to Brickman to confirm their prior conversation. In the letter, Murphy stated "As agreed the lease will be in the same form as Manchester [lease] and the rent will be at $3.25 per sq. ft.” During the ensuing months in 1973, Brickman hired attorneys, architects and engineers to help him complete this project. Many problems had to be overcome before the shopping center could be built. For example, extensive blasting would be necessary; a river passing through the site would have to be re-routed; a zoning change would be necessary. On or about July 31, 1973, a second representative of defendant, named Deery, sent a proposed lease to the plaintiff. Although the plaintiff signed this lease, neither party maintains that this lease ever took effect. Defendant’s executive committee never approved that lease but recommended that the lease be renegotiated. On September 12, 1973, the executive committee approved a revised lease. On January 4, 1974, the plaintiff executed the revised lease and forwarded it to the defendant. Article 6 of this lease contained a provision that the defendant would not be required to deliver an executed copy of the lease until the plaintiff had provided satisfactory proof with regard to (1) the title to the premises, (2) zoning changes and (3) subordination agreements. Article 26 contained a merger clause that it was the only agreement between the parties. Section 3 of article 27 contained a cancellation provision. The defendant contends that the lease, as executed by the plaintiff, contained a cancellation date of September 1, 1975. Under section 3, the defendant had the right to cancel before September 1, 1976. If the defendant did not cancel by September 1, 1976, it could not cancel until the fifth anniversary date, January 4, 1979. As will be developed more fully below, the plaintiff denied at trial that he had ever executed a lease containing the September 1, 1975 cancellation date. During the summer and early fall of 1974, the plaintiff eventually satisfied the requirements of article 6 by securing (1) the proper zoning classification, (2) title to the property, and (3) the necessary subordination agreements. On or about November 15, 1974, the defendant executed and returned the January 4, 1974 lease to the
Dissent
Cases cited
- Textile Capitol Building Corp. v. Wendel Foundation 279 NY 769 p. 738
- McKinley v. Hessen 202 NY 24 p. 739
- Fogelson v. Rackfay Construction Co. 300 NY 334 at 340 p. 739
- Breger v. Hampshire Country Club, Inc. 23 NY2d 958 p. 739