— Order unanimously reversed, without costs, and motion denied. Memorandum: Contrary to the finding at Special Term, we find that the claim of respondent-appellant (hereinafter referred to as contractor) in Appeal No. 1 with respect to the disputed change orders did not accrue until October 30, 1975, and that therefore the notice of claim dated November 8, 1975 and served November 20, 1975 was timely under subdivision 1 of section 3813 of the Education Law. Special Term apparently concluded that inasmuch as the contractor in its letter to the architect of the petitioners-respondents (hereinafter referred to as the school district), dated October 30, 1975, claimed interest on certain of the items, the contractor’s claim accrued on the most recent date from which interest was calculated (viz., July, 1975). There were, however, other orders listed in the same letter for which interest was not claimed and which were referred to in the letter as "new change orders.” One of these orders, "Drawing SKA-8,” dated August 29, 1975, is referred to in two previous letters from the architect to the contractor dated September 9, 1975 and September 16, 1975, and appears to involve correction of drainage and paving projects. Clearly, this work had not been completed as of the September 16, 1975 letter and it is reasonable to conclude that at that time the contractor did not know the extent of his damages with respect to these corrections. The October 30, 1975 letter is the first time the record indicates that the projects were complete or at least that a monetary amount was ascertainable with respect to "SKA-8.” Thus we conclude that the claim accrued on October 30, 1975. When a number of distinct items within a contract are in dispute, the claim accrues when damages are ascertainable for all of the disputed items (see Matter of Board of Educ. v Wager Constr. Corp., 37 NY2d 283 , 291; Almar Constr. Corp. v Hughes & Sons, 58 AD2d 615 , app dsmd 42 NY2d 1009 ). The notice of claim also demanded final payment under the contract. Inasmuch as the change orders under the contract had not been completed prior to October 30, 1975, this portion of the claim was also timely (see Matter of Board of Educ. v Wager Constr. Corp., supra; Wm. J. Schmitt, Inc. v Penfield Cent. School Dist., 54 AD2d 1100 ; Shalman v Board of Educ., 31 AD2d 338 ). The school district argues that the notice of claim dated November 8, 1975 was inadequate because it did not set forth facts sufficient to allow the school district to investigate the
Cases cited
- In re the Arbitration between the Board of Education & Wager Construction Corp. 37 NY2d 283 at 291 p. 808, p. 809
- Almar Construction Corp. v. P. M. Hughes & Sons, Inc. 58 AD2d 615 p. 808, p. 809
- Almar Construction Corp. v. P. M. Hughes & Sons, Inc. 42 NY2d 1009 p. 808
- Shalman v. Board of Education of Central School District No. 1 31 AD2d 338 p. 808, p. 809
- P. J. Panzeca, Inc. v. Board of Education 29 NY2d 508 at 509 p. 809
- Central School District No. 3 v. Samuel Kosoff & Sons, Inc. 53 AD2d 1058 p. 809
- Scherman v. Board of Education 37 NY2d 839 p. 809