Majority
Cross appeals from a judgment in favor of claimant, entered August 26, 1977, upon a decision of the Court of Claims. This claim arises out of a contract between claimant and the State of New York for reconstruction of .44 mile of Flushing Avenue in Maspeth, New York. The purpose of the project was to eliminate grade crossings of two branches of the Long Island Railroad on Flushing Avenue. The proposed plan required the erection of two railroad and three highway bridges over a reconstructed and recessed roadway. In addition, two new service roads were to be built, with retaining walls positioned between them and the recessed portion of Flushing Avenue. Related work included the improvement of detour roads and the relocation of utility and sewer lines. Both rail and vehicular traffic were to be maintained at all times. Bids for the contract were advertised on February 20, 1967. They were due on March 23, 1967 and the contract was signed on May 8, 1967. Work was commenced on June 12, 1967, with a completion date set for December 31, 1968. Although the project was not accepted by the State until September 29, 1970, the record demonstrates that the work was substantially completed by December 15, 1969, 11 Vi months after the scheduled completion date. Claimant seeks to hold the State liable in damages for the increased costs in time and material it allegedly incurred as a result of faulty and misleading designs and plans which caused a series of stoppages and delays during the course of construction. The claim, filed on March 10, 1972, originally contained 33 causes of action. On this appeal we are only concerned with 15 of them. Claimant appeals from so much of the judgment of the Court of Claims as dismissed seven of its causes of action, while the State cross-appeals from the portions which made awards to claimant on eight causes of action. In a lengthy and comprehensive decision, the Court of Claims addressed each cause of action separately and found the State liable for certain extra expenses incurred by claimant and made awards for direct costs. However, the causes of action seeking damages for the increased consequential or indirect costs flowing therefrom as a result of the delays occasioned by the State were dismissed. In its decision on Causes of Action Nos. 9 through 13, the Court of Claims concluded that difficulties encountered by claimant in the installation and lagging of "soldier beams” were the State’s responsibility. Soldier beams are metal piles, driven vertically into the ground, designed to support other structures or forms which, under provisions of the contract, were required to be erected prior to excavation for, among other things, the development of a
2nd Cause of Action:
Field Supervision and Field Office Personnel -1/1/69 to 12/15/69
Field Office Expenses (same period) Additional Labor (same period)
Excavation Trench excavation Concrete labor Gravel backfill labor Cleanup labor
$108,654.51
92,778.54
94,487.67
27,216.02
27,436.77
$101,114.00
19,044.00
350,574.00
Home Office Overhead and Profit Idle Equipment
52,586.00
452,773.00
$ 976,091.00
4th Cause of Action: Holiday Pay
5th Cause of Action: Traffic, Maintenance and Protection 15th Cause of action: Trench Excavation
7,997.00
75.760.00
26.475.00
Total
$1,086,323.00
There only remains for consideration whether the interests of justice require an apportionment of the damages awarded in this case (Fehlhaber Corp. v State of New York, 65 AD2d 119 , supra; Grow Constr. Co. v State of New York, supra; Public Constructors v State of New York, 55 AD2d 368 ). The record plainly demonstrates numerous failures on the part of the State yet, in retrospect, claimant could have mitigated some of its damages by, among other things, insisting upon the predrilling of the nested boulders at an early date and by making a more studied evaluation of the test boring
Cases cited
- Grow Construction Co. v. State 56 AD2d 95 p. 685
- Peckham Road Co. v. State 32 AD2d 139 p. 685
- Peckham Road Co. v. State 28 NY2d 734 p. 685
- Fehlhaber Corp. & Horn Construction Co. v. State 65 AD2d 119 at 125-126 p. 685, p. 686
- D'Angelo v. State 41 AD2d 77 p. 686
- Public Constructors, Inc. v. State 55 AD2d 368 p. 686