75 A.D.2d 675 Court N.Y. App. Div. Decision date 1980-04-10 Docket Claim No. 54855 English

Contents

Majority

p. 675
Fehlhaber Corporation and Horn Construction Co., Inc., Respondent, v State of New York, Appellant.
(Claim No. 54855.)

Motion for reargument or, in the alternative, for permission to appeal to the Court of Appeals, denied, without costs. A prior motion by appellant requesting the same relief was denied by order of this court entered January 14, 1980. Appellant acquired no new appeal rights by reason of the resettlement granted on January 14, 1980 since that order merely allowed appellant’s motion for a partial stay of the underlying judgment of the Court of Claims as modified by this court’s original order entered August 24, 1979 (see e.g.,

p. 676
May v May, 66 AD2d 918 ). Mahoney, P. J., Sweeney, Kane and Main, JJ., concur.