Appeal from a judgment of the Supreme Court, entered June 18, 1979 in Broome County, upon a verdict rendered at a Trial Term, without a jury, in favor of plaintiff. In July, 1975, defendant Broome County contacted plaintiff Trane Company concerning the breakdown of a large centrifugal chiller air-conditioning unit installed in the library of the Broome County Community College. The unit had been manufactured by plaintiff and had been installed in the library approximately eight years prior thereto. Eventually, the plaintiff conducted a detailed inspection of the air-conditioning unit and discovered that it was in a serious state of disrepair, being filled with water, rust and corrosion. Plaintiff advised the defendant that major repairs were required and entered into an agreement with the defendant to perform such repairs on a time and material formula basis. Plaintiff completed the work and submitted invoices to the appellant in the amount of $27,868.45. The county comptroller, however, rejected the invoices for failure to conform with the competitive bidding provisions of subdivision 1 of section 103 of the General Municipal Law and section 1202 of the Broome County Charter. Sometime thereafter, the plaintiff commenced an action in which it sought, among other things, to recover the amount due under its contract. The trial court, sitting without a jury, determined that the work involved services requiring skill and expertise and that, therefore, the contract with plaintiff was not subject to competitive bidding. We agree. Generally, a contract which is let in violation of a competitive bidding statute is illegal and void, and a party thereto may not recover payment either for the price agreed
Cases cited
- Gerzof v. Sweeney 22 NY2d 297 at 304 p. 1016
- Doyle Alarm Co. v. Reville 65 AD2d 916 p. 1016
- American Totalisator Co. v. Western Regional Off-Track Betting Corp. 44 AD2d 750 p. 1016
- Hurd v. Erie County 34 AD2d 289 p. 1016