— Cross appeals from a judgment in favor of claimant, entered August 5, 1980, upon a decision of the Court of Claims (Murray, J.). By agreement dated September 8, 1967 and approved by the State Comptroller on September 19, 1967, claimant, as sole bidder, was awarded a public highway construction contract known as the Lark-Dove Arterial, Interstate Route 504, Albany County, at a cost of $34,884,584. Claimant immediately commenced work on the project and was scheduled to complete it by August 8, 1971. However, due to a variety of problems, work on the project was not finally completed until December 31, 1972 and accepted by the State on February 3,1973. Claimant commenced this action against the State in the Court of Claims on April 16, 1974 alleging various breaches of contract and claiming damages exceeding $9,600,000. Over $7,200,000 of that figure was alleged to be damages for delays in completion of the contract caused by the State. Disputes concerning various quantities of materials paid for by the State under the contract accounted for approximately $570,000 of the damages alleged, Various other items composed the remainder of the claim. Following a trial, the Court of Claims partially allowed the claim. Although the trial court failed to find any liability on the part of the State regarding that portion of the claim dealing with damages due
* This portion of the contract provides: “Item 76X — Maintenance and Protection of Traffic on Sections Opened to Traffic Prior to Acceptance. 1. Description. Under this item the Contractor shall maintain traffic and protect the public from damage to person and property whenever directed, in writing, by the District Engineer to open to public traffic any portion of new permanent mainline pavement or structures on new location or any portion of new permanent mainline pavement substantially on old location on which public traffic is not maintained during construction under Item 76. The Contractor shall also maintain traffic and protect the public from damage to person and property on any connector or ramp used by such traffic.”
Cases cited
- Zara Contracting Co. v. State 7 AD2d 956 at 957 p. 699
- Yonkers Contracting Co. v. New York State Thruway Authority 25 NY2d 1 at 4 p. 699