Majority
Order, Supreme Court, Bronx County (Norma Ruiz, J.), entered May 14, 2012, which, insofar as appealed from as limited by the briefs, granted plaintiff’s motion for partial summary judgment on the issue of liability on his Labor Law § 240 (1) claim, and granted the motion of third-party defendant Sherry Hill Painting Corporation (Sherry Hill) for summary judgment dismissing the third-party contractual indemnification claim, unanimously affirmed, without costs.
Plaintiff was injured when he fell after the six-foot baker’s
Given that the scaffold was inadequate in the first instance, any failure by plaintiff to hydrate himself could not be the sole proximate cause of his injuries (see Blake v Neighborhood Hous. Servs. of N.Y. City, 1 NY3d 280 , 290 [2003]; Lajqi v New York City Tr. Auth., 23 AD3d 159 [1st Dept 2005]).
Dismissal of the contractual indemnification claim against Sherry Hill was proper, since there was no indemnification agreement in existence at the time of the accident, and nothing indicates that the terms and conditions on the back of the purchase order, which contains the indemnification clause, were to have a retroactive effect (see Regno v City of New York, 88 AD3d 610 [1st Dept 2011]; Temmel v 1515 Broadway Assoc., L.P., 18 AD3d 364 , 365-366 [1st Dept 2005]).
We have considered defendants’ course of conduct argument and find it unavailing.
Concur—Tom, J.E, Acosta, Román, Feinman and Clark, JJ.
Cases cited
- Vergara v. SS 133 West 21, LLC 21 AD3d 279 p. 637
- Blake v. Neighborhood Housing Services of New York City, Inc. 1 NY3d 280 at 290 p. 637
- Temmel v. 1515 Broadway Associates, L.P. 18 AD3d 364 at 365-366 p. 637