Majority
The condominium unit owners validly ratified the board’s renovation plans, based on knowledge they obtained through formal and informal communications (see e.g. Skytrack Condominium Bd. of Mgrs. v Windberk Partners, 167 AD2d 381 [2d Dept 1990]). We reject defendants’ argument that the ratification vote was invalid because the unit owners were not disinterested; defendants were at least equally conflicted. Plaintiff showed sufficient cause for its second summary judgment motion (see Varsity Tr. v Board of Educ. of City of N.Y., 300 AD2d 38 , 39 [1st Dept 2002]). The factual issue whether the unit owners’ knowledge of the renovations was sufficient to support their ratification of the board’s arguably voidable resolution was raised by defendants in a surreply long after the final submissions on the initial summary judgment motion. Concur— Andrias, J.P, Saxe, Freedman and Gische, JJ.
Cases cited
- Varsity Transit, Inc. v. Board of Education 300 AD2d 38 at 39 p. 463