Majority
In a proceeding pursuant to CPLR 7511 to confirm an arbitration award, the Town of Huntington appeals from an order of the Supreme Court, Suffolk County (Farneti, J.), dated May 9, 2012, which, inter alia, granted the petition.
Ordered that the order is affirmed, with costs.
In the arbitration award at issue, the arbitrator determined that the Town of Huntington breached a collective bargaining agreement by failing to pay certain legal fees on behalf of the grievant. The Supreme Court properly concluded that the arbitrator’s determination did not clearly violate a strong public policy, was not totally or completely irrational, and did not manifestly exceed a specific, enumerated limitation on the
The Town’s remaining contentions are without merit.
Accordingly, the Supreme Court properly granted the petition to confirm the arbitration award.
Skelos, J.E, Austin, Sgroi and LaSalle, JJ., concur.
Cases cited
- Erin Construction & Development Co. v. Meltzer 58 AD3d 729 p. 744
- In re the Arbitration between Security & Law Enforcement Employees & County of Albany 96 AD2d 976 at 978 p. 744
- In re the Arbitration between Security & Law Enforcement Employees & County of Albany 61 NY2d 965 p. 744
- Zimmer v. Town of Brookhaven 247 AD2d 109 p. 744