Majority
In an action to recover damages for personal injuries, (1) the defendant appeals from a judgment of the Supreme Court, Kangs County (Silber, J.), entered July 10, 2012, which, upon a jury
Ordered that the cross appeal from the judgment and the appeal from the order dated September 27, 2012, are dismissed as academic in light of our determination on the appeal from the judgment; and it is further,
Ordered that the judgment is modified, on the law, by deleting the provision thereof awarding prejudgment interest to the plaintiff at the rate of 4% per annum from March 5, 2004, and substituting therefor a provision awarding prejudgment interest to the plaintiff at the rate of 4% per annum from May 24, 2011; as so modified, the judgment is affirmed, and the matter is remitted to the Supreme Court, Kings County, for the recalculation of prejudgment interest in accordance herewith, and the entry of an appropriate amended judgment thereafter; and it is further,
Ordered that one bill of costs is awarded to the plaintiff.
This is the third time that this case has come before this Court. On the first appeal by the defendant, New York City Housing Authority, this Court reversed a judgment entered upon a decision of the trial court (Douglas, J.), made on the eve of trial, concluding that the plaintiff was entitled to summary judgment on the issue of liability on the cause of action alleging a violation of Labor Law § 241-a, and upon a jury verdict on the issue of damages. This Court, however, affirmed the jury’s findings of fact on the issue of damages, and remitted the matter to the Supreme Court, Kings County, for a trial on the issue of li
The plaintiff and his coworker, both elevator mechanics, were repairing one of two elevators sharing a common shaftway in a building, while the other elevator remained in operation. Upon returning to the elevators after making a telephone call, the plaintiff summoned the operational elevator, stepped part of the way into it, looked up into the shaftway, and called out to his coworker, who was on top of the cab of the elevator being repaired, to ask on which floor the coworker was working. As the coworker turned to answer, he knocked a tool off the top of that elevator’s cab and the tool fell, injuring the plaintiffs right eye. The plaintiff commenced this personal injury action against the defendant, the owner of the building, alleging, inter alia, violations of Labor Law §§ 200, 241 (6) and 241-a.
At the third trial, which was conducted on the issue of liability only, the plaintiff proceeded primarily on the theory that the defendant’s failure to install a vertical barrier between the two elevators sharing the shaftway in which he was working constituted violations of Labor Law §§ 200 and 241 (6), and that those violations proximately caused his injury. All witnesses who could recall the appearance and condition of the shaftway agreed that there was no vertical barrier in place at the time of the accident. On May 24, 2011, the jury rendered a verdict on the issue of liability, finding that the defendant violated Labor Law §§ 200 and 241 (6). In an order dated January 12, 2012, the Supreme Court denied the defendant’s motion pursuant to CPLR 4404 (a) to set aside the verdict and for judgment as a matter of law dismissing the complaint or, in the alternative, to set aside the verdict as contrary to the weight of the evidence and for a new trial. The Supreme Court thereafter entered judgment in favor of the plaintiff which, among other things, awarded the plaintiff prejudgment interest from March 5, 2004, the date of the jury verdict on the issue of.damages.
To be held liable pursuant to Labor Law § 200 in a case such
Labor Law § 241 (6) “imposes a nondelegable duty of reasonable care upon owners and contractors ‘to provide reasonable and adequate protection and safety’ to persons employed in, or lawfully frequenting, all areas in which construction, excavation or demolition work is being performed” (Rizzuto v L.A. Wenger Contr. Co., 91 NY2d 343 , 348 [1998], quoting Labor Law § 241 [6]). Section 23-2.5 (b) (3) of the Industrial Code requires that “[w]here any elevator is being installed, repaired or replaced and persons are working in the shaft, a solid or wire mesh partition shall be provided where necessary to prevent such persons from contacting any adjacent operable elevator or counterweight” (12 NYCRR 23-2.5 [b] [3]). “The Industrial Code should be sensibly interpreted and applied to effectuate its purpose of protecting construction laborers against hazards in the workplace” (St. Louis v Town of N. Elba, 16 NY3d 411 , 416 [2011]).
Accordingly, the Supreme Court properly denied the defendants’ motion pursuant to CPLR 4404 (a) to set aside the verdict and for judgment as a matter of law or, in the alternative, to set aside the verdict as contrary to the weight of the evidence and for a new trial.
The Supreme Court, erred, however, in computing prejudgment interest from March 5, 2004, the date of the jury verdict on the issue of damages, because liability was not established at that time (see Love v State of New York, 78 NY2d 540 , 544 [1991]). As set forth by the defendant in its proposed counter-judgment, the Supreme Court should have computed the prejudgment interest from May 24, 2011, the date that liability was determined by the jury (see id.; see also Grobman v Chernoff, 15 NY3d 525 , 528-529 [2010]).
The defendant’s remaining contention is without merit.
In light of our determination, we do not reach the plaintiffs contentions, raised on his cross appeal from the judgment, concerning the dismissal of the cause of action alleging a violation of Labor Law § 241-a.
Rivera, J.R, Sgroi, Hinds-Radix and Maltese, JJ., concur.
Cases cited
- Brownrigg v. New York City Housing Authority 29 AD3d 721 p. 506
- Brownrigg v. New York City Housing Authority 70 AD3d 619 p. 506
- Gallagher v. Resnick 107 AD3d 942 at 945 p. 507
- Szczepanski v. Dandrea Construction Corp. 90 AD3d 642 at 644 p. 507
- Rodriguez v. Gany 82 AD3d 863 at 865 p. 507
- Rojas v. Schwartz 74 AD3d 1046 at 1046-1047 p. 507
- Ortega v. Puccia 57 AD3d 54 at 61 p. 507
- Lombardi v. Stout 80 NY2d 290 at 295 p. 507
- Lazier v. Strickland Avenue Corp. 50 AD3d 641 at 642 p. 507
- Capolino v. Judlau Contracting, Inc. 46 AD3d 733 p. 507
- Aloi v. Structure-Tone, Inc. 2 AD3d 375 at 376 p. 507
- Lolik v. Big V Supermarkets, Inc. 86 NY2d 744 at 746 p. 507
- Rizzuto v. L.A. Wenger Contracting Co. 91 NY2d 343 at 348 p. 507
- St. Louis v. Town of North Elba 16 NY3d 411 at 416 p. 507
- Love v. State 78 NY2d 540 at 544 p. 508
- Grobman v. Chernoff 15 NY3d 525 at 528-529 p. 508