Majority
Order, Supreme Court, New York County (Peter H. Moulton, J.), entered June 23, 2014, which vacated a temporary restraining order and denied petitioners’ motion for a preliminary injunction staying any work on the subject project, and any further public financing for the project, until a further environmental review is conducted, unanimously affirmed, without costs.
In this proceeding brought pursuant to CPLR article 78 seeking to, among other things, annul a negative declaration of
Supreme Court properly determined that the impact of HFA’s financing of the project is slight, since the project can be built “as of right” without HFA’s financing (see Matter of Committee to Preserve Brighton Beach & Manhattan Beach v Council of City of N.Y., 214 AD2d 335 , 337 [1st Dept 1995], lv denied 87 NY2d 802 [1995]).
We have considered petitioners’ remaining contentions and find them unavailing. Concur — Friedman, J.P., Andrias, Saxe, Richter and Gische, JJ. [Prior Case History; 2014 NY Slip Op 31577 (U).]
Cases cited
- Gilliland v. Acquafredda Enterprises, LLC 92 AD3d 19 at 24-25 p. 436
- Riverkeeper, Inc. v. Planning Board 9 NY3d 219 at 231-232 p. 436
- Rusciano & Son Corp. v. Kiernan 300 AD2d 590 at 590-591 p. 436
- Jaffee v. RCI Corp. 119 AD2d 854 at 855 p. 436
- Chinese Staff & Worker's Ass'n v. Burden 88 AD3d 425 at 433 p. 436
- Chinese Staff & Workers' Ass'n v. Burden 19 NY3d 922 p. 436