Majority
Cross appeals from an order of the Supreme Court (Aulisi, J.), entered March 6, 2014 in Fulton County, which, among other things, denied respondent’s cross application pursuant to CPLR 7511 to confirm a modified arbitration award.
At all times relevant, petitioner was the prime contractor on a public work project awarded by the Department of Transportation for construction work on a portion of State Route 17 in Sullivan County. In conjunction therewith, petitioner entered into a subcontract with respondent to clear and grub approximately 75 acres of land in exchange for $406,250. The parties’ subcontract provided that “[a]ny controversy of [sic] claim” arising out of or related to the subcontract would be settled by arbitration.
In October 2010, respondent filed a demand for arbitration contending, among other things, that it was entitled to extra payment for clearing and grubbing additional acreage over and above that required by the underlying subcontract, in response
Following receipt of the arbitrator’s original award, respondent sought “clarification” thereof — contending that the arbitrator “misunderstood the parties [‘] stipulation.” Specifically, respondent asserted that petitioner had withheld the $82,512.35 referenced in the award prior to the actual arbitration and, further, that the parties had stipulated that such sum “could continue to be withheld pending the passage of time or other resolution between the parties.” According to respondent, the $82,512.35 at issue was not intended to be applied against any award made in its favor and, therefore, the arbitrator should not have deducted that amount from the total sum due and payable to respondent.[2] Petitioner opposed the relief sought, arguing that the requested clarification would amount to a re-determination of the merits and, further, that the adjustment sought by respondent did not qualify as the “correction of a clerical, typographical, technical or computational error” in the original award within the meaning of CPLR 7509 and 7511 (c) (1). In so doing, petitioner did not address the substance of respondent’s claim — namely, that petitioner was, in effect, receiving a double credit as to (at least) the $82,512.35 at issue.
The arbitrator thereafter issued a modified award, which granted the full $150,250 to respondent and deleted any reference to the previous “credits,” thereby making no award of damages with respect to petitioner’s counterclaim. As to the basis for such modification, the arbitrator noted, “It now appears that the amounts in question were withheld from [respondent’s] final payment, and therefore should not, of course,
1 The parties’ stipulation was not reduced to writing, the hearing minutes were not transcribed and the parties’ post-hearing submissions do not appear in the record.
2 The request for clarification made no mention of the $13,806 in “stipulated backcharges.”
Supreme Court declined to vacate the original award based upon respondent’s failure to comply with the notice of claims provision set forth in the parties’ arbitration agreement, finding that the arbitrator’s decision not to enforce this clause was both rational and based upon consideration of the underlying equities. Similarly, Supreme Court denied petitioner’s request to vacate the modified award based upon respondent’s untimely modification request, finding — in essence — that the arbitrator acted within her authority in entertaining a request that, due to law office failure, was filed one day beyond the 20-day period set forth in CPLR 7509. As to the merits, Supreme Court agreed that the arbitrator exceeded her authority in issuing the modified award, as such modification went beyond the mere correction of a computational error within the meaning of CPLR 7511 (c) (1), and granted petitioner’s request to vacate this award. As to the original award, Supreme Court found that the arbitrator — by neglecting to delineate and address the effect of the parties’ purported stipulation — failed to make “a final and definite award [upon] the subject matter submitted” (CPLR 7511 [b] [1] [iii]). Accordingly, Supreme Court vacated the original award as well and remanded the matter to the arbitrator for a rehearing and redetermination of the issues— including the existence and/or content of the parties’ alleged stipulation and the corresponding effect, if any, upon petitioner’s counterclaim. Respondent now appeals, seeking reinstatement of the modified award, and petitioner cross appeals, contending that there is no basis upon which to remand this matter to the arbitrator for further proceedings.
We affirm. Initially, we reject petitioner’s assertion that respondent failed to comply with what it characterizes as a condition precedent to arbitration. The parties’ dispute in this regard centers around a notice of claim clause contained within the arbitration agreement, which required that any claim for an
As to the merits, we agree with petitioner that the arbitrator’s modification of the original award exceeded the narrow grounds set forth in CPLR 7511 (c). A review of the modified award reveals that the arbitrator did not simply correct a “miscalculation of figures ... in the [original] award” (CPLR 7511 [c] [1]) but, rather, made new factual findings as to the applicability of the parties’ apparent stipulation relative to petitioner’s counterclaim and its corresponding impact upon the moneys awarded, i.e., the arbitrator impermissibly revisited the merits of the parties’ dispute. Under these circumstances, the modified award was properly vacated (see CPLR 7509, 7511 [c]; Avamer Assoc., L.P. v 57 St. Assoc., L.P., 67 AD3d 483 , 484 [2009]; cf. Matter of Outback Steakhouse, Inc. v Contracting Mgt., Inc., 58 AD3d 855 , 855 [2009]).
We also are persuaded that Supreme Court properly vacated the original arbitration award and remanded the matter to the arbitrator for a rehearing (see CPLR 7511 [d]). CPLR 7511 (b)
McCarthy, J.P., Lynch and Clark, JJ., concur.
Ordered that the order is affirmed, without costs.
Cases cited
- New York City Transit Authority v. Transport Workers' Union of America 6 NY3d 332 at 336 p. 1215
- In re the Arbitration between Bianchi & Katz 111 AD3d 1012 at 1013 p. 1215
- In re the Arbitration between Falzone & New York Mutual Fire Insurance 15 NY3d 530 at 534 p. 1216
- Aftor v. Geico Insurance 110 AD3d 1062 at 1064 p. 1216