Majority
Ordered that the order is affirmed, with costs.
“[A] property owner who contracts with a general contractor does not become liable to a subcontractor on a quasi contract theory unless it expressly consents to pay for the subcontractor’s performance” (Perma Pave Contr. Corp. v Paerdegat Boat & Racquet Club, 156 AD2d 550 , 551 [1989]). “The mere fact that the [owners] consented to the improvements and received some benefit from the [subcontractor’s] activities is insufficient to recover on such a theory; the [subcontractor] must also show that it was working for the [owners] when it performed its work resulting in unjust enrichment” (Yellowstone Indus. v Vinco Mar. Mgt., 305 AD2d 587 , 588 [2003]). Here, the defendants Lighthouse Marina, Inc., Larry’s Lighthouse Marina, Inc., and Pierro-Galasso, Inc., formerly known as DeMarco-Galasso, Inc. (hereinafter collectively the owners), demonstrated their prima facie entitlement to judgment as a matter of law by submitting evidence demonstrating that, at the time the plaintiff performed the subject work, the plaintiff was not working for them, and instead was working as a subcontractor for the defendant V.M.A. Concrete Construction, Inc., a contractor hired by the owners to install, among other things, the concrete foundation for a boat storage building (see Alvarez v Prospect Hosp., 68 NY2d 320 , 324 [1986]; Yellowstone Indus. v Vinco Mar. Mgt., 305 AD2d at 588 ). In opposition, the evidence submitted by the plaintiff failed to raise a triable issue of fact as to whether it was working for the owners when it performed its work (see Yellowstone Indus. v Vinco Mar. Mgt., 305 AD2d at 588 ; see generally Mandarin Trading Ltd. v Wildenstein, 16 NY3d 173 , 182 [2011]; Zere Real Estate Servs., Inc. v Parr Gen. Contr. Co., Inc., 102 AD3d 770 , 772 [2013]; cf. Westinghouse Elec. Supply Co. v Brosseau & Co., 156 AD2d 851 , 853 [1989]). Moreover, the plaintiff failed to show that the motion should have been denied as premature (see CPLR 3212 [f]; 1375 Equities Corp. v Buildgreen Solutions, LLC, 120 AD3d 783 , 784 [2014]).
Accordingly, the Supreme Court properly granted the owners’ motion for summary judgment dismissing the complaint insofar as asserted against them.
Mastro, J.P., Chambers, Austin and Miller, JJ., concur.
Cases cited
- Perma Pave Contracting Corp. v. Paerdegat Boat & Racquet Club, Inc. 156 AD2d 550 at 551 p. 846
- Yellowstone Industries, Inc. v. Vinco Marine Management, Inc. 305 AD2d 587 at 588 p. 846
- Alvarez v. Prospect Hospital 68 NY2d 320 at 324 p. 846
- Mandarin Trading Ltd. v. Wildenstein 16 NY3d 173 at 182 p. 846
- Zere Real Estate Services, Inc. v. Parr General Contracting Co. 102 AD3d 770 at 772 p. 846
- Westinghouse Electric Supply Co. v. R.P. Brosseau & Co. 156 AD2d 851 at 853 p. 846
- 1375 Equities Corp. v. Buildgreen Solutions, LLC 120 AD3d 783 at 784 p. 846