Majority
In an action, inter alia, to recover damages for breach of contract, the plaintiff appeals from a judgment of the Supreme Court, Suffolk County (Pines, J.), entered September 12, 2013, which, upon a jury verdict finding, among other things, in effect, that it breached the parties’ construction contract, is in favor of the defendants and against it in the principal sum of $2,211,000.
Ordered that the judgment is affirmed, with costs.
In March 2007, the defendants entered into a contract to purchase real property located on Butter Lane, in Bridgehampton, from nonparty Dimitri Boylan (hereafter Dimitri). The real property was improved with a partially constructed residence. At the same time the defendants entered into the contract of sale, they entered into a construction contract with the plaintiff, Vivir of LI, Inc., formerly known as Opus Vivir,
Opus commenced this action against the defendants seeking, inter alia, to recover allegedly outstanding monies due under the construction contract and change orders. The defendants counterclaimed, alleging, among other things, that Opus materially breached the construction contract in a number of ways, and overcharged them with respect to the change orders by adding an unstated markup cost to the total amount of each change order. The defendants alleged, and argued at trial, that the construction contract did not provide for markups, and that, during the negotiation process, Julian stated in an email that any changes following execution of the construction contract would be at “cost,” without “mark up.” Opus contended that change order markups were always contemplated by the parties, and that they did not need to be listed as a separate item on the change orders. Following a jury trial limited to the issue of the parties’ respective breach of contract claims, at which parol evidence with respect to the change order markup issue was admitted into evidence, the jury returned a verdict in favor of the defendants awarding them damages in the principal sum of $2,211,000.
Opus’s contention that the jury verdict must be set aside because parol evidence with respect to the change order markup issue was incorrectly admitted into evidence is without merit. A written agreement that is complete, clear, and unambiguous on its face must be enforced to give effect to the meaning of its terms and the reasonable expectations of the parties, and the court should determine the intent of the parties from within the four corners of the contract without looking to extrinsic evidence to create ambiguities (see South Rd.
Here, contrary to Opus’s contention, parol evidence was properly admitted into evidence to explain the ambiguous phrase “cost to Owner” in the change order provision of the construction contract, inasmuch as the term “cost” was not defined, and could have various meanings, including one limited to labor and material costs without an additional markup. Accordingly, parol evidence, such as the email from Opus’s principal, Julian, stating that change orders would not include markups, which does not otherwise vary or contradict the construction contract, was permitted (see Laskey v Rubel Corp., 303 NY 69 [1951]; Levy v Keslow, 213 AD2d 276 [1995]).
Opus’s remaining contention is without merit.
Mastro, J.P., Austin, Cohen and Barros, JJ., concur.
Cases cited
- South Road Associates, LLC v. International Business Machines Corp. 4 NY3d 272 at 277 p. 964
- W.W.W. Associates, Inc. v. Giancontieri 77 NY2d 157 at 162 p. 964
- Belle Harbor Washington Hotel, Inc. v. Jefferson Omega Corp. 17 AD3d 612 p. 964
- Breed v. Insurance Co. of North America 46 NY2d 351 at 355 p. 964
- Annis v. Phillips 256 AD2d 531 at 531 p. 964
- Stone v. Schulz 231 AD2d 707 at 707 p. 964
- Katz v. American Technical Industries, Inc. 96 AD2d 932 at 933 p. 964
- Schron v. Troutman Sanders LLP 20 NY3d 430 p. 964
- Laskey v. Rubel Corp. 303 NY 69 p. 964