Majority
Appeal from an order of the Supreme Court (Platkin, J.), entered March 18, 2014 in Albany County, which, among other things, granted defendant’s motion for partial summary judgment dismissing the complaint.
In April 2001, plaintiff contracted with defendant to be the prime contractor in charge of installation of heat, ventilation and air conditioning (hereinafter HVAC) during a major renovation project at a state psychiatric center. Plaintiffs completion of the work was significantly delayed by a multitude of design errors and other issues. As a result, plaintiff commenced the instant action asserting breach of contract and several other causes of action. Following extensive discovery, defendant moved for partial summary judgment seeking, as relevant here, to dismiss plaintiff’s causes of action seeking damages for delay and extra work. Supreme Court granted the motion, finding that these claims were barred by a mandatory notice provision and a no-damages-for-delay clause in the parties’ contract. Plaintiff appeals.
As a general rule, “contract clauses exculpating the contractee from liability to the contractor for damages resulting from delays in performance of the contract work” are valid and enforceable (Harrison & Burrowes Bridge Constructors, Inc. v State of New York, 42 AD3d 779 , 782 [2007]; see Kalisch-Jarcho, Inc. v City of New York, 58 NY2d 377 , 384 [1983]). However, even where the contract contains such a clause, there are several recognized exceptions. As relevant here, a contractor may still recover for “delays caused by the contractee’s bad faith or its willful, malicious, or grossly negligent conduct” (Corinno Civetta Constr. Corp. v City of New York, 67 NY2d 297 , 309
Gross negligence differs in kind from claims of ordinary negligence, and requires a showing of “conduct that evinces a reckless disregard for the rights of others or smacks of intentional wrongdoing” (Soja v Keystone Trozze, LLC, 106 AD3d 1168 , 1170 [2013] [internal quotation marks and citations omitted]; accord Finsel v Wachala, 79 AD3d 1402 , 1404 [2010]; see Abacus Fed. Sav. Bank v ADT Sec. Servs., Inc., 18 NY3d 675 , 683 [2012]). Here, plaintiff claims that defendant was grossly negligent in permitting plaintiff to bid on the project when it knew of and failed to disclose defects in the HVAC design that would necessarily cause problems and delays. Plaintiff relies upon the testimony of an engineer who was employed by defendant to monitor the adequacy of the HVAC design work being performed by plaintiff’s consultant, Crandell Associates, Architects and Facility Planners, PC. According to plaintiff, reports completed by defendant’s engineer at various stages of Crandell’s design work reveal that he identified, but nonetheless recklessly failed to address, several potential design flaws, including spatial limitations that could — and later did — interfere with fitting HVAC ducts into interstitial ceiling spaces. However, the engineer testified that his role was limited to “identify[ing] the deficiencies],” rather than “mandating] recommendations to [the] consultants.” Further, his reports reveal that he relied on representations by Crandell’s subconsultant that it would investigate the issues that he had identified.
Even if the engineer or defendant had a duty to follow up on these representations and ensure that the design flaws were
Next, plaintiff contends that defendant’s efforts to schedule and coordinate the work of the numerous contractors involved in the project were so incompetent that they evinced a reckless disregard for the delays that were bound to result. As plaintiff contends, the contract required defendant to facilitate the preparation of a “critical path method” work schedule that was to be released shortly after construction began. This schedule was not implemented until five months after construction started, and it ultimately proved to be so inadequate that defendant abandoned it. The record reveals that significant delays resulted from these failures. However, it also reveals that it was the contractual responsibility of the general contractor, not defendant, to finalize and update the schedule, and that defendant made proactive efforts to coordinate the work, including holding weekly progress meetings for purposes of scheduling and coordination. The contract contains a provision expressly exculpating defendant from liability resulting from “delays attendant upon any construction schedule approved by [defendant],” in addition to the no-damages-for-delay clause. Given the scope of the contract’s several exculpatory clauses, defendant’s scheduling failures demonstrate, at worst, “inept administration or poor planning” and do not constitute gross negligence (Commercial Elec. Contrs., Inc. v Pavarini Constr. Co., Inc., 50 AD3d 316 , 318 [2008]; see Plato Gen. Constr. Corp. / EMCO Tech Constr. Corp., JV, LLC v Dormitory Auth. of State of N.Y., 89 AD3d at 823 ; T.J.D. Constr. Co. v City of New York, 295 AD2d 180 , 180 [2002]).
We reject plaintiff’s contention that the cumulative effect of
Plaintiff also contends that the no-damages-for-delay clause does not bar its claim because of issues of fact as to whether defendant dealt with plaintiff in bad faith. In support of this argument, plaintiff primarily relies upon opinions expressed in a single email sent by an employee of defendant, who later passed away. We agree with Supreme Court that the document was inadmissible as plaintiff failed to lay a foundation for its admission as a business record in accord with the established statutory requirements (see CPLR 4518; State of New York v 158th St. & Riverside Dr. Hous. Co., Inc., 100 AD3d 1293 , 1297 [2012], lv denied 20 NY3d 858 [2013]).[1] The mere fact that the email was originally produced by defendant during discovery does not, as plaintiff contends, alter that requirement. Further, even assuming that the email had been admissible, the statements of its author fell well short of evidencing any “sinister intention” or “dishonest purpose” (Kalisch-Jarcho, Inc. v City of New York, 58 NY2d at 385, 385 n 5) on defendant’s part. As plaintiff offered no other evidence of bad faith, it has failed to demonstrate a triable issue of fact as to this exception to the no-damages-for-delay clause.[2]
Finally, plaintiff attempts to claim compensation for tasks
1 Plaintiff argues that defendant waived this argument by failing to timely object. However, the record reveals that plaintiff did not declare its intention to admit the document as a business record until after defendant objected to its admission on the ground that the email’s author was deceased. Defendant objected at its first opportunity when the business record theory was raised.
2 Plaintiffs allegations that defendant manifested bad faith by favoring another contractor at plaintiff’s expense constitute nothing more than speculation or examples of “inept administration or poor planning” that, as previously noted, do not constitute gross negligence (Commercial Elec. Contrs., Inc. v Pavarini Constr. Co., Inc., 50 AD3d at 318 ). The further conten *1397 tion that the email constituted a party admission, raised for the first time on appeal, is unpreserved.
Egan Jr., Rose and Lynch, JJ., concur. Ordered that the order is affirmed, without costs.
Cases cited
- Kalisch-Jarcho, Inc. v. City of New York 58 NY2d 377 at 384 p. 1393
- Corinno Civetta Construction Corp. v. City of New York 67 NY2d 297 at 309 p. 1393
- Plato General Construction Corp./EMCO Tech Construction Corp. JV, LLC v. Dormitory Authority 89 AD3d 819 at 823 p. 1394
- Blue Water Environmental, Inc. v. Incorporated Village of Bayville 44 AD3d 807 at 810 p. 1394
- Fowler, Rodriguez, Kingsmill, Flint, Gray & Chalos, LLP v. Island Properties, LLC 38 AD3d 831 at 833 p. 1394
- Soja v. Keystone Trozze, LLC 106 AD3d 1168 at 1170 p. 1394
- Finsel v. Wachala 79 AD3d 1402 at 1404 p. 1394
- Abacus Federal Savings Bank v. ADT Security Services, Inc. 18 NY3d 675 at 683 p. 1394
- LoDuca Associates, Inc. v. PMS Construction Management Corp. 91 AD3d 485 at 486 p. 1395
- Gottlieb Contracting, Inc. v. City of New York 86 AD2d 588 at 589 p. 1395
- Gottlieb Contracting, Inc. v. City of New York 58 NY2d 1051 p. 1395
- T.J.D. Construction Co. v. City of New York 295 AD2d 180 at 180 p. 1395
- Bovis Lend Lease (LMB), Inc. v. Lower Manhattan Development Corp. 108 AD3d 135 at 147 p. 1396
- Princetel, LLC v. Buckley 95 AD3d 855 at 856 p. 1396
- Welch v. Hannigan 20 NY3d 994 p. 1396
- State v. 158th Street & Riverside Drive Housing Co. 100 AD3d 1293 at 1297 p. 1396
- Fahs Construction Group, Inc. v. State 123 AD3d 1311 at 1311-1312 p. 1397
- A.H.A. General Construction, Inc. v. New York City Housing Authority 92 NY2d 20 at 30-31 p. 1397
- Chenango Forks Central School District v. New York State Public Employment Relations Board 95 AD3d 1479 at 1484 p. 1397
- Chenango Forks Central School District v. New York State Public Employment Relations Board 21 NY3d 255 p. 1397
- Sicoli & Massaro, Inc. v. Niagara Falls Housing Authority 281 AD2d 966 at 966 p. 1397