Majority
In an action to recover damages for breach of contract, the plaintiff appeals from an order of the Supreme Court, Rockland County (Loehr, J.), dated July 22, 2013, which granted the defendant’s motion for summary judgment dismissing the complaint.
Ordered that the order is reversed, on the law, with costs, and the defendant’s motion for summary judgment dismissing the complaint is denied.
The plaintiff alleged that the defendant, the County of Rockland, breached a contract between the parties for a project to stabilize the banks of the Nauraushaun Brook. The County terminated the contract on the ground that the plaintiff was unable to successfully complete the project. The plaintiff, however, alleged that the County caused and created delays that prevented it from completing the project.
Furthermore, while the County established, prima facie, that the plaintiff’s claim for delay damages was precluded by the no-damages-for-delay clause in the parties’ contract, the plaintiff raised triable issues of fact as to whether the delays resulted from the County’s bad faith or its willful, malicious, or grossly negligent conduct, and/or whether the delays resulted from the County’s breach of a fundamental obligation of the contract (see Corinno Civetta Constr. Corp. v City of New York, 67 NY2d 297 , 309 [1986]; Castagna & Son v Board of Educ. of City of NY [New Dorp High School], 173 AD2d 405 [1991]).
Chambers, J.P., Hall, Cohen and Maltese, JJ., concur.
Cases cited
- Central Irrigation Supply v. Putnam Country Club Associates, LLC 27 AD3d 684 at 685 p. 1050
- Corinno Civetta Construction Corp. v. City of New York 67 NY2d 297 at 309 p. 1050
- Castagna & Son, Inc. v. Board of Education 173 AD2d 405 p. 1050