Majority
It is hereby ordered that the order so appealed from is unanimously reversed on the law without costs, the motions of defendant-appellant are granted, and the complaint and the cross claims of defendants Liverpool Central School District, Liverpool Central School District Board of Education, Natare Corporation, and Bette & Cring, LLC, formerly known as Barry, Bette & Led Duke, Inc., against it are dismissed.
Memorandum: Plaintiff Chandra M. Hewitt, by her father, and plaintiff father, individually, commenced this action seeking damages for injuries sustained by Chandra when she lacerated her wrist on strips of metal in the water collection and filtration system of a swimming pool owned and operated by defendants Liverpool Central School District and the Liverpool Central School District Board of Education (collectively, School District defendants). Plaintiffs alleged that the injuries were caused by, inter alia, the negligent design, manufacture and installation of the water collection and filtration system, and that defendant Klepper, Hahn & Hyatt, Engineers and Landscape Architect, P.C. (KHH) was liable for damages because the School District defendants had hired KHH to provide structural and mechanical engineering services during a renovation of the swimming pool. After some discovery, KHH moved for summary judgment dismissing the complaint against it pursuant to CPLR 3212 (b) and (i), and KHH moved separately pursuant to those subdivisions for summary judgment dismissing “any and all current or prospective cross claims” against it. We note that KHH did not name any specific cross claimants in that motion, but the moving papers of KHH included the answers with cross claims against it from the School District defendants, defendant Natare Corporation (Natare), and defendant Bette & Cring, LLC, formerly known as Barry, Bette & Led Duke, Inc. (Bette & Cring). Supreme Court denied KHH’s motions pursuant to CPLR 3212 (f), without prejudice to renew pursuant to CPLR 3212 (b) and (i) following additional discovery. We reverse.
We conclude with respect to both motions that KHH met its initial burden pursuant to CPLR 3212 (b) by submitting
In light of our determination, we do not address KHH’s contention that it was entitled to summary judgment pursuant to CPLR 3212 (i). Present — Scudder, P.J., Centra, Peradotto, Lindley and Valentino, JJ.
Cases cited
- Simon v. Granite Building 2, LLC 114 AD3d 749 at 755 p. 1509
- Zuckerman v. City of New York 49 NY2d 557 at 562 p. 1509
- Preferred Capital, Inc. v. PBK, Inc. 309 AD2d 1168 at 1169 p. 1509
- Newman v. Regent Contracting Corp. 31 AD3d 1133 at 1135 p. 1509
- State Farm Fire & Casualty Co. v. Ricci 96 AD3d 1571 at 1574 p. 1509
- Kirbis v. LPCiminelli, Inc. 90 AD3d 1581 at 1582-1583 p. 1509
- WILJEFF, LLC v. United Realty Management Corp. 82 AD3d 1616 at 1617 p. 1509