Majority
Order, Supreme Court, New York County (Barry R. Ostrager, J.), entered October 14, 2015, which denied plaintiff’s motion for summary judgment on its breach of contract cause of action seeking the principal amount of $46,960, plus interest pursuant to CPLR 5001 (a), unanimously reversed, on the law, with costs, the motion granted, and the matter remanded for further proceedings regarding interest in accordance with this decision.
Plaintiff subcontractor made a prima facie showing of the existence of the parties’ agreement, its performance thereunder, and defendant general contractor’s failure to perform, resulting in harm to plaintiff (see Harris v Seward Park Hous. Corp., 79 AD3d 425 , 426 [1st Dept 2010]). Plaintiff established the amount due from defendant by submitting an email exchange between the parties, reflecting their agreement on the amount due, and defendant’s representation that payment would be made as soon as it received payment from third-party defendant owner.
Because the parties on appeal have not addressed the date from which interest shall be computed pursuant to CPLR 5001, we remand for further proceedings and a determination regarding interest (see Peachy v Rosenzweig, 215 AD2d 301 [1st Dept 1995]; see also Delulio v 320-57 Corp., 99 AD2d 253 [1st Dept 1984]). Upon such determination, the Clerk shall calculate the amount of interest and enter judgment accordingly (see CPLR 5001 [c]).
Concur — Mazzarelli, J.P., Moskowitz, ManzanetDaniels and Gesmer, JJ.
Cases cited
- Harris v. Seward Park Housing Corp. 79 AD3d 425 at 426 p. 515
- West-Fair Electric Contractors v. Aetna Casualty & Surety Co. 87 NY2d 148 at 158 p. 516
- Hugh O'Kane Electric Co. v. MasTec North America, Inc. 19 AD3d 126 at 126 p. 516
- Rugova v. Davis 112 AD3d 404 at 404-405 p. 516
- Delulio v. 320-57 Corp. 99 AD2d 253 p. 516