Majority
In an action, inter alia, to recover damages for breach of contract, the plaintiff appeals, as limited by his brief, from (1) so much of an order of the Supreme Court, Nassau County (Driscoll, J.), dated September 21, 2015, as reserved decision on that branch of the defendants’ motion which was pursuant to CPLR 3211 (a) (5) to dismiss as time-barred so much of the first cause of action as was predicated upon loans that alleg
Ordered that the appeal from the order dated September 21, 2015, is dismissed, as the plaintiff is not aggrieved by the portion of the order appealed from (see CPLR 5511; Mixon v TBV, Inc., 76 AD3d 144 , 156-157 [2010]; see also Katz v Katz, 68 AD2d 536 , 542-543 [1979]), and, in any event, the portion of the order appealed from was superseded by the order dated January 7, 2016 (see Zdunczyk v Ginther, 15 AD3d 574 , 574 [2005]); and it is further,
Ordered that the order dated January 7, 2016, is affirmed insofar as appealed from; and it is further,
Ordered that one bill of costs is awarded to the defendants.
The plaintiff commenced this action in November 2013, to recover damages for, among other things, breach of contract. The plaintiff alleged that he made a series of loans to the defendants which totaled more than $1,024,997.18. The amended complaint reflects that the first of these loans was made no later than July 2006, and that the last two loans were made in December 2007. The amended complaint alleged that the parties’ agreement did not specify any particular time when these loans would become due (c/I UCC 3-108), and that the defendants agreed to repay the loans within three months after the plaintiff made a demand for repayment. The alleged agreement did not place any conditions upon the plaintiff’s right to demand repayment such that the plaintiff was free to demand repayment at any time.
The defendants moved, inter alia, pursuant to CPLR 3211 (a) (5) to dismiss as time-barred so much of the first cause of action as was predicated upon loans that allegedly were made more than six years prior to the commencement of the action. In the first order appealed from, the Supreme Court, among other things, reserved decision on that branch of the defendants’ motion. In the second order appealed from, the Supreme Court, inter alia, granted that branch of the defendants’ motion.
In resolving a motion to dismiss pursuant to CPLR 3211 (a) (5), this Court must accept the facts as alleged in the complaint as true and accord the plaintiff the benefit of every possible favorable inference (see Faison v Lewis, 25 NY3d 220 , 224
“The time within which an action must be commenced, except as otherwise expressly prescribed, shall be computed from the time the cause of action accrued to the time the claim is interposed” (CPLR 203 [a]; see Hahn Automotive Warehouse, Inc. v American Zurich Ins. Co., 18 NY3d 765 , 770 [2012]). “In contract actions ... a claim generally accrues at the time of the breach” (Hahn Automotive Warehouse, Inc. v American Zurich Ins. Co., 18 NY3d at 770 ; see Ely-Cruikshank Co. v Bank of Montreal, 81 NY2d 399 , 402 [1993]).
“Where, as here, the claim is for payment of a sum of money allegedly owed pursuant to a contract, the cause of action accrues when the plaintiff ‘possesses a legal right to demand payment’ ” (Swift v New York Med. Coll., 25 AD3d 686 , 687 [2006], quoting Matter of Prote Contr. Co. v Board of Educ. of City of N. Y., 198 AD2d 418 , 420 [1993]; see City of New York v State of New York, 40 NY2d 659 , 668 [1976]; Minskoff Grant Realty & Mgt. Corp. v 211 Mgr. Corp., 71 AD3d 843 , 845 [2010]; Kuo v Wall St. Mtge. Bankers, Ltd., 65 AD3d 1089 , 1090 [2009]). Since a lender who has made a loan which is repayable on demand has the immediate legal right to demand payment upon the issuance of the loan {see McMullen v Rafferty, 89 NY 456 , 459 [1882]; Environics, Inc. v Pratt, 50 AD2d 552 , 552-553 [1975]; Knapp v Greene, 29 NYS 350 [Sup Ct, Gen Term, 1st Dept 1894]), courts have consistently held that “[a] cause of action to recover on a note which is payable on demand accrues at the time of its execution” {Morrison v Zaglool, 88 AD3d 856 , 858 [2011]; see Phoenix Acquisition Corp. v Campcore, Inc., 81 NY2d 138 , 143 [1993]; McMullen v Rafferty, 89 NY at 459 ; See v Ach, 56 AD3d 457 , 458 [2008]; Lynford v Williams, 34 AD3d 761 , 762 [2006]; Shelley v Dixon Equities, 300 AD2d 566 , 567 [2002];
Here, the parties’ agreement, as alleged in the amended complaint, provided that the sums loaned to the defendants were repayable on demand. Accordingly, the plaintiff possessed a legal right to demand payment at the time that each loan was advanced to the defendants, and the statute of limitations began to run at each of those respective times (see Hahn Automotive Warehouse, Inc. v American Zurich Ins. Co., 18 NY3d at 771 ; Phoenix Acquisition Corp. v Campcore, Inc., 81 NY2d at 143 ; McMullen v Rafferty, 89 NY at 459 ; Morrison v Zaglool, 88 AD3d at 858 ; See v Ach, 56 AD3d at 458 ; Lynford v Williams, 34 AD3d at 762 ; Shelley v Dixon Equities, 300 AD2d at 567 ). Contrary to the plaintiff’s contention, the three-month period for repayment following a demand did not constitute a condition that had to be fulfilled before the right to final payment arose (see Environics, Inc. v Pratt, 50 AD2d 552 , 552-553 [1975]; Knapp v Greene, 29 NYS 350 [1894]; see also CPLR 206 [a]; see generally 81 NY Jur 2d, Negotiable Instruments and Other Commercial Paper § 665; cf. John J. Kassner & Co. v City of New York, 46 NY2d 544 , 550 [1979]). Accordingly, the Supreme Court properly granted that branch of the defendants’ motion which was pursuant to CPLR 3211 (a) (5) to dismiss as time-barred so much of the first cause of action as was predicated upon loans that allegedly were made more than six years prior to the commencement of the action.
Balkin, J.P., Cohen, Miller and Brathwaite Nelson, JJ., concur.
Cases cited
- Katz v. Katz 68 AD2d 536 at 542-543 p. 963
- Zdunczyk v. Ginther 15 AD3d 574 at 574 p. 963
- Faison v. Lewis 25 NY3d 220 at 224 p. 963
- Ford v. Phillips 121 AD3d 1232 at 1234 p. 964
- Leon v. Martinez 84 NY2d 83 at 87-88 p. 964
- Stewart v. GDC Tower 138 AD3d 729 at 729 p. 964
- Campone v. Panos 142 AD3d 1126 at 1127 p. 964
- Barry v. Cadman Towers, Inc. 136 AD3d 951 at 952 p. 964
- Hahn Automotive Warehouse, Inc. v. American Zurich Insurance 18 NY3d 765 at 770 p. 964
- Ely-Cruikshank Co. v. Bank of Montreal 81 NY2d 399 at 402 p. 964
- Swift v. New York Medical College 25 AD3d 686 at 687 p. 964
- City of New York v. State 40 NY2d 659 at 668 p. 964
- Minskoff Grant Realty & Management Corp. v. 211 Manager Corp. 71 AD3d 843 at 845 p. 964
- Kuo v. Wall Street Mortgage Bankers, Ltd. 65 AD3d 1089 at 1090 p. 964
- McMullen v. Rafferty 89 NY 456 at 459 p. 964
- Knapp v. Greene 29 NYS 350 p. 964, p. 965
- Morrison v. Zaglool 88 AD3d 856 at 858 p. 964
- Phoenix Acquisition Corp. v. Campcore, Inc. 81 NY2d 138 at 143 p. 964
- Lynford v. Williams 34 AD3d 761 at 762 p. 964
- Shelley v. Dixon Equities 300 AD2d 566 at 567 p. 964
- John J. Kassner & Co. v. City of New York 46 NY2d 544 at 550 p. 965