Appeal from an order of the Supreme Court (Ellis, J.), entered June 27, 2016 in Franklin County, which, among other things, granted a motion by defendants Martin Sexton and Georganne Sexton to vacate two default judgments entered against them.
In May 2012, defendants Martin Sexton and Georganne Sexton (hereinafter collectively referred to as defendants) contracted with plaintiff Nils Edward Luderowski, an architect, to design a camp for defendants’ lakefront property in the Town of Santa Clara, Franklin County.[1] Defendants subsequently contracted with plaintiff Redwing Construction Co., Inc. to build the camp in accordance with Luderowski’s designs. In 2013, however, disputes arose among the parties. By August 2013, both Luderowski and Redwing (hereinafter collectively referred to as plaintiffs) filed separate mechanic’s liens against the camp, and they later commenced separate actions against defendants seeking, among other relief, money damages and the foreclosure of their respective liens. Defendants responded by filing pre-answer motions to dismiss in each of the actions and, alternatively, moving to join the actions for trial. In separate amended decisions and orders, Supreme Court, among other things, denied defendants’ motions to dismiss, but granted their motions to join the actions for trial.
Following Supreme Court’s denial of their motions to dismiss, defendants failed to answer until nearly one year later, after plaintiffs served them with a notice of their intention to apply for default judgments. Defendants promptly answered upon receiving plaintiffs’ notice, but plaintiffs rejected it as untimely and obtained default judgments. Defendants then swiftly moved to vacate the default judgments pursuant to CPLR 5015 (a) (1), and the court granted their motion. Plaintiffs now appeal, and we affirm.
To prevail on their motion to vacate the default judgments, defendants were required to demonstrate both a reasonable excuse for their failure to timely answer and the existence of a potentially meritorious defense to the underlying causes of action (see CPLR 5015 [a] [1]; Gage v Village of Catskill, 144 AD3d 1365 , 1366 [2016]; Abel v Estate of Collins, 73 AD3d 1423 , 1424 [2010]). The reasonableness of their proffered
* Defendants and Luderowski mutually agreed to terminate their contract in September 2012 after defendants experienced unforeseen financial difficulties.
Here, defendants attribute their failure to timely serve an answer to law office failure, namely, defense counsel’s admittedly mistaken belief that one of his former associates had timely answered. This associate, who had been handling the matter, left the firm around the time that plaintiffs served defendants with the amended decision and order, thus commencing the period within which defendants had to answer. Defense counsel incorrectly assumed that this associate had filed and served the answer in the course of “wrap [ping] up” his work for the firm and did not discover this error until after plaintiffs served him with notice of their intention to seek default judgments.
Under the circumstances, we find that defendants’ default was attributable to an excusable instance of law office failure (see CPLR 2005; Hoffman v Kessler, 28 AD3d 718 , 718-719 [2006]; Goldman v Cotter, 10 AD3d 289 , 291 [2004]; Polir Constr. v Etingin, 297 AD2d 509 , 513 [2002]). The record reveals that, once the error was discovered, it was promptly cured (see Puchner v Nastke, 91 AD3d at 1262 ; Action Lawn & Landscaping v East Glenville Fire Dist., 254 AD2d 585 , 587 [1998]). Defendants’ participation in significant motion practice before defaulting also indicates that they had no intention of
McCarthy, J.P., Egan Jr. and Devine, JJ., concur.
Ordered that the order is affirmed, with costs.
Cases cited
- Gage v. Village of Catskill 144 AD3d 1365 at 1366 p. 918
- Abel v. Collins 73 AD3d 1423 at 1424 p. 918
- Puchner v. Nastke 91 AD3d 1261 at 1262 p. 920
- Fried v. Jacob Holding, Inc. 110 AD3d 56 at 60 p. 920
- Passeri v. Tomlins 141 AD3d 816 at 819 p. 920
- Baptist Health Nursing & Rehabilitation Center, Inc. v. Baxter 140 AD3d 1386 at 1388 p. 920
- State v. Bayramov 98 AD3d 811 at 812 p. 920
- Hayes v. Village of Middleburgh 140 AD3d 1359 at 1362 p. 920
- People v. Landa 28 AD3d 718 at 718-719 p. 920
- Goldman v. Cotter 10 AD3d 289 at 291 p. 920
- Polir Construction, Inc. v. Etingin 297 AD2d 509 at 513 p. 920
- Action Lawn & Landscaping, Inc. v. East Glenville Fire District 254 AD2d 585 at 587 p. 920
- Catlyn & Derzee, Inc. v. Amedore Land Developers, LLC 132 AD3d 1202 at 1206-1207 p. 921
- Accadia Site Contracting, Inc. v. Erie County Water Authority 115 AD3d 1351 at 1353 p. 921