Majority
Appeal from a judgment of the Supreme Court (Williams, J.), entered July 28, 2005 in Saratoga County, which dismissed petitioner’s application, in a proceeding pursuant to CPLR article 78, to review a determination of respondent adopting a project labor agreement to be used in the construction of a public library.
The Clifton Park-Halfmoon Public Library District was established by the Legislature in 2001 (see L 2001, ch 370) and, thereafter, voters of the district approved construction of a 55,000 square foot library with an estimated project cost of $15 million. In preparation for the construction project, respondent commissioned a detailed study regarding use of a project labor agreement (hereinafter PLA) and that study determined that a PLA would, among other things, minimize delays and reduce costs. Respondent negotiated the terms of the PLA with the Greater Capital Region Building and Construction Trades Council and began receiving bids, with successful bidders agreeing to abide by the PLA. Petitioner, a nonunion construction company that bids on and performs public works contracts, brought this proceeding contending that the use of a PLA on the project was improper. The relief requested by petitioner included that no contracts be awarded under the PLA, that the PLA be declared unlawful and that the construction project be stayed. Supreme Court dismissed the petition, finding, among other things, that respondent set forth sufficient evidence to establish that the PLA advanced the central purposes of the competitive bidding statutes, that is, protection of the public fisc and prevention of favoritism, improvidence, fraud and corruption (see Matter of New York State Ch., Inc., Associated Gen. Contrs. of Am. v New York State Thruway Auth., 88 NY2d 56 , 68 [1996]). Petitioner appeals.
Initially, we observe that the bids had been submitted and contracts awarded by the time of Supreme Court’s decision, petitioner did not seek a stay from this Court pending appeal, and counsel represented during oral argument that construction on the project has progressed substantially toward completion. Moreover, the relief requested both in the original petition and in petitioner’s brief on appeal is now either impossible to
Cardona, P.J., Spain, Carpinello and Mugglin, JJ., concur. Ordered that the appeal is dismissed, as moot, without costs.
Cases cited
- New York State Chapter, Inc. v. New York State Thruway Authority 88 NY2d 56 at 68 p. 1046
- Paden v. Planning Board of Mamakating 270 AD2d 626 at 626 p. 1048
- Save the Pine Bush, Inc. v. Cuomo 200 AD2d 859 at 860 p. 1048
- Harbour v. Riedell 172 AD2d 920 at 921 p. 1048
- Gaetani v. Grippen 183 AD2d 989 at 990 p. 1048
- In re Grand Jury Subpoenas for Local 17, 135, 257 & 608 of United Brotherhood of Carpenters & Joiners of America 72 NY2d 307 at 311 p. 1048
- New York Hotel Trades Council & Hotel Ass'n v. Park South Hotel Corp. 488 US 966 p. 1048
- Hearst Corp. v. Clyne 50 NY2d 707 at 714-715 p. 1048
- Empire State Chapter of Associated Builders & Contractors, Inc. v. Board of Education of City of Buffalo 269 AD2d 801 at 801-802 p. 1048
- Albany Specialties, Inc. v. County of Orange 240 AD2d 739 at 740-741 p. 1048