Order, Supreme Court, New York County (Judith J. Gische, J.), entered on or about February 3, 2006, which granted defendant and third-party plaintiff subcontractor Heilman’s motion for summary judgment on its cause of action for contractual indemnification against third-party defendant sub-subcontractor Schroder, and denied Schroder’s cross motion for summary judgment dismissing Heilman’s third-party complaint and defendant construction manager TDX’s cross claims against it, unanimously affirmed, without costs.
No issue of fact exists as to Heilman’s negligence, the deposition testimony demonstrating that Hellman did not exercise any supervisory control over plaintiff’s work, that Schroder, plaintiff’s employer, did exercise such control, and that TDX was responsible for cleanup of the debris that allegedly caused plaintiff to fall (see O’Sullivan v IDI Constr. Co., Inc., 28 AD3d 225 , 226-227 [2006], affd 7 NY3d 805 [2006]; Conforti v Bovis Lend Lease LMB, Inc., 37 AD3d 235 [2007]). Testimony that
Cases cited
- O'Sullivan v. IDI Construction Co. 28 AD3d 225 at 226-227 p. 477
- O'Sullivan v. IDI Construction Co. 7 NY3d 805 p. 477
- Cahill v. Triborough Bridge & Tunnel Authority 31 AD3d 347 at 350 p. 478
- Gordon v. American Museum of Natural History 67 NY2d 836 p. 478
- Colozzo v. National Center Foundation, Inc. 30 AD3d 251 at 252 p. 478
- Cavanaugh v. 4518 Associates 9 AD3d 14 at 18 p. 478
- Mahoney v. Turner Construction Co. 37 AD3d 377 at 379 p. 478