Majority
In an action to recover damages for breach of contract, the defendant appeals from an order of the Supreme Court, Suffolk County (Cohalan, J.), dated May 23, 2006, which denied its motion pursuant to CPLR 3211 (a) (5) to dismiss the complaint for failure to comply with Education Law § 3813 (1) and (2-b).
Ordered that the order is reversed, on the law, with costs, and the defendant’s motion pursuant to CPLR 3211 (a) (5) to dismiss the complaint for failure to comply with Education Law § 3813 (1) and (2-b) is granted.
Here, the defendant established that the plaintiffs request for payment had been constructively rejected no later than February 2004, and thus, the cause of action accrued more than three months prior to service of the notice of claim in July 2004 and more than one year before commencement of the action in May 2005 (see Capstone Enters, of Port Chester, Inc. v Valhalla Union Free School Dist., 27 AD3d 411 , 412 [2006]).
Contrary to the plaintiffs contention, the defendant was not estopped from asserting its defense pursuant to Education Law § 3813 (see Bronco Bus Corp. v City of Yonkers Bd. of Educ., 250 AD2d 718 , 719 [1998]).
The plaintiffs remaining contentions are without merit. Rivera, J.P., Ritter, Goldstein and Angiolillo, JJ., concur.
Cases cited
- C.S.A. Contracting Corp. v. New York City School Construction Authority 5 NY3d 189 at 192 p. 481
- Parochial Bus Systems, Inc. v. Board of Education 60 NY2d 539 at 547 p. 481
- Hawthorne Cedar Knolls Union Free School District v. Carey & Walsh, Inc. 36 AD3d 810 p. 481
- Capstone Enterprises of Port Chester, Inc. v. Valhalla Union Free School District 27 AD3d 411 at 412 p. 481
- Bronco Bus Corp. v. City of Yonkers Board of Education 250 AD2d 718 at 719 p. 481