Majority
Appeal from an order of the Supreme Court, Monroe County (David Michael Barry, J.), entered September 7, 2007 in a personal injury action. The order, inter alia, denied the motion of defendant Wright Real Estate, L.L.C. to vacate a default judgment and extend its time to answer.
It is hereby ordered that the order so appealed from is unanimously reversed on the law without costs, the motion is granted, the judgment entered August 9, 2006 is vacated, defendant Wright Real Estate, L.L.C. is granted 20 days from service of the order of this Court with notice of entry to serve and file an answer, and the cross motion is dismissed.
Memorandum: Plaintiff commenced this Labor Law and common-law negligence action seeking damages for injuries he allegedly sustained while working at a construction site. Defendant Wright Real Estate, L.L.C. (LLC) failed to answer the complaint, and Supreme Court (Egan, J.) granted plaintiff’s motion seeking a default judgment against the LLC. We agree with the LLC and defendants Claude G. Wright and Claude H. Wright, doing business as Wright Real Estate Partnership (Partnership), that Supreme Court (Barry, J.) erred in denying the motion of the LLC to vacate the default judgment and extend the LLC’s time to answer. “A defendant seeking to vacate a default under [CPLR 5015 (a)] must demonstrate a reasonable excuse for its delay in appearing and answering the complaint and a meritorious defense to the action” (Eugene Di Lorenzo, Inc. v A.C. Dutton Lbr. Co., 67 NY2d 138 , 141 [1986]). Here, after the Partnership, as owner, entered into the contracts for the construction project, the Partnership converted into the
Cases cited
- Eugene Di Lorenzo, Inc. v. A. C. Dutton Lumber Co. 67 NY2d 138 at 141 p. 1059
- Hayes v. R.S. Maher & Son, Inc. 303 AD2d 1018 p. 1060
- Mayville v. Wal-Mart Stores, Inc. 273 AD2d 944 at 945 p. 1060
- Estate of Witzigman v. Drew 48 AD3d 1172 p. 1060