Majority
In an action, inter alia, to recover damages for breach of contract, the plaintiff appeals, as limited by its brief, from so much of a judgment of the Supreme Court, Nassau County (McCarty, J.), entered June 5, 2009, as, upon a decision of the same court dated October 7, 2008, made after a nonjury trial, is in favor of the defendants and against it dismissing the complaint.
Ordered that the judgment is affirmed insofar as appealed from, with costs.
In reviewing a determination made after a nonjury trial, the power of this Court is as broad as that of the trial court, and we may render the judgment it finds warranted by the facts, bearing in mind that in a close case, the trial judge had the advantage of seeing the witnesses (see Northern Westchester Professional Park Assoc. v Town of Bedford, 60 NY2d 492 , 499 [1983]; Parr v Ronkonkoma Realty Venture I, LLC, 65 AD3d 1199 , 1201 [2009]). On this record, we discern no basis to disturb the trial court’s findings of fact or conclusions of law.
The Supreme Court properly credited the testimony of the witnesses in determining that there was an express contract between the parties requiring that the plaintiff be paid on a fixed rate basis for certain electrical service, work, equipment, and materials provided, thus precluding the existence of a contract implied in fact for payment of all electrical service, work, equipment, and materials on a time and materials basis (see Jemzura v Jemzura, 36 NY2d 496 , 503-504 [1975]; see Zimmer v Town of Brookhaven, 247 AD2d 109 [1998]). Contrary to the plaintiffs contention on appeal, “[a] contract cannot be implied in fact where the facts are inconsistent with its existence . . . or where there is an express contract covering the subject-matter involved” (Miller v Schloss, 218 NY 400 , 406-407 [1916]; see Tjoa v Butterfield Mem. Hosp., 205 AD2d 526 , 526-527 [1994]).
Similarly, the Supreme Court properly determined that the plaintiff failed to establish its entitlement to recover damages for the extra work performed on a theory of quantum meruit because it failed to demonstrate the reasonable value of the extra work performed (see generally Miranco Contr., Inc. v Perel, 57 AD3d 956 , 957-958 [2008]; see Najjar Indus. v City of New York, 87 AD2d 329 [1982], affd 68 NY2d 943 [1986]).
Finally, the Supreme Court properly determined that the plaintiff failed to establish the requisite elements for recovery on a theory of account stated (see Heelan Realty & Dev. Corp. v Ocskasy, 27 AD3d 620 , 621 [2006]; Tridee Assoc., Inc. v Board of Educ. of City of N.Y., 22 AD3d 833 , 834 [2005]). Mastro, J.P., Florio, Belen and Roman, JJ., concur.
Cases cited
- Northern Westchester Professional Park Associates v. Town of Bedford 60 NY2d 492 at 499 p. 1155
- Parr v. Ronkonkoma Realty Venture I, LLC 65 AD3d 1199 at 1201 p. 1155
- Jemzura v. Jemzura 36 NY2d 496 at 503-504 p. 1155
- Zimmer v. Town of Brookhaven 247 AD2d 109 p. 1155
- Miller v. Schloss 218 NY 400 at 406-407 p. 1155
- T. Seng Tjoa v. Julia Butterfield Memorial Hospital 205 AD2d 526 at 526-527 p. 1155
- Hi-Amp Electrical Contr. Corp. v. Maximum Mechanical Corp. 37 AD3d 541 at 541-542 p. 1156
- Howdy Jones Construction Co. v. Parklaw Realty, Inc. 76 AD2d 1018 p. 1156
- Howdy Jones Construction Co. v. Parklaw Realty, Inc. 53 NY2d 718 p. 1156
- Bilotta Construction Corp. v. Village of Mamaroneck 199 AD2d 230 at 231 p. 1156
- Savin Brothers, Inc. v. State 62 AD2d 511 at 516 p. 1156
- Savin Bros. v. State 47 NY2d 934 p. 1156
- Miranco Contracting, Inc. v. Perel 57 AD3d 956 at 957-958 p. 1156
- Najjar Industries, Inc. v. City of New York 87 AD2d 329 p. 1156
- Najjar Industries, Inc. v. City of New York 68 NY2d 943 p. 1156
- Heelan Realty & Development Corp. v. Ocskasy 27 AD3d 620 at 621 p. 1156
- Tridee Associates, Inc. v. Board of Education 22 AD3d 833 at 834 p. 1156