Majority
Appeal from an order of the Court of Claims (Collins, J.), entered September 25, 2009, which partially granted defendants’ motion to partially dismiss the claim.
Claimant M/A-Com, Inc. (hereinafter claimant) entered into a master agreement with defendant State of New York for claimant to create a statewide wireless network that would facilitate better communication for public safety and public service agencies. The agreement stated that the project would begin with claimant establishing the network in two counties in western New York, referred to as the primary regional build. After the State approved of the network in that region, the State would pay claimant for the completed work and claimant would begin expanding the network throughout New York. During the initial phase, a change order was apparently issued wherein claimant agreed to update a communications system in New York City, known as the Metro 21 system, while continuing to work on the primary regional build. Claimant alleges that it has spent $15 million on the Metro 21 system.
The State terminated the contract due to alleged deficiencies within the network. Claimants commenced this action claiming, as relevant on this appeal, that the State breached the contract and was unjustly enriched by claimant’s work on the Metro 21 system. Defendants moved to dismiss all of the causes of action except for breach of contract. With one exception not relevant to this appeal, the Court of Claims granted defendants’ motion. Claimants appeal, limiting their argument to the court’s dismissal of the unjust enrichment claim regarding work done on the Metro 21 system. We affirm.
“The existence of a valid and enforceable written contract governing a particular subject matter ordinarily precludes
The result here is different than under the general rule, however, because claimant was dealing with the State. Any contract with a state agency above a monetary threshold must be approved by the Comptroller (see State Finance Law § 112 [2] [a]).[1] If a change order that addresses the Metro 21 system was approved by the Comptroller, then claimant can proceed under a breach of contract theory and may not recover for unjust enrichment. On the other hand, if no change order addresses the Metro 21 system, and there is thus no written contract concerning that system approved by the Comptroller, then the statute bars claimant from recovering for work done on that system (see Parsa v State of New York, 64 NY2d 143 , 147 [1984]). Unlike a private party, the State’s acceptance of benefits furnished under a contract made without the proper authorization cannot “estop [the State] from challenging the validity of the contract or from denying liability pursuant to it” (id. at 147; see Hamlin Beach Camping, Catering, & Concessions Corp. v State of New York, 303 AD2d 849 , 853 [2003]; Rosefsky v State of New York, 205 AD2d 120 , 124 [1994]). While State Finance Law § 112 does not prevent recovery under a quasi contract theory where a contract is implied-in-law to
* Claimant alleges that it spent $15 million on the Metro 21 system. That amount exceeds the statute’s monetary threshold, which was $15,000 at the relevant time (see State Finance Law former § 112 [2] [a]).
Peters, J.P., Rose, Lahtinen and Garry, JJ., concur. Ordered that the order is affirmed, without costs.
Cases cited
- Clark-Fitzpatrick, Inc. v. Long Island Rail Road 70 NY2d 382 at 388 p. 1294
- Plumitallo v. Hudson Atlantic Land Co. 74 AD3d 1038 at 1039 p. 1294
- Goldman v. Simon Property Group, Inc. 58 AD3d 208 at 220 p. 1294
- Schwartz v. Pierce 57 AD3d 1348 at 1353 p. 1294
- Foster v. Kovner 44 AD3d 23 at 29 p. 1294
- Parsa v. State 64 NY2d 143 at 147 p. 1294
- Hamlin Beach Camping, Catering, & Concessions Corp. v. State 303 AD2d 849 at 853 p. 1294
- Koffman v. State 205 AD2d 120 at 124 p. 1294