Majority
In an action to recover damages for personal injuries, the defendants appeal, as limited by their brief, from so much of an order of the Supreme Court, Kings County (Schmidt, J.), dated October 13, 2009, as denied that branch of their motion which was for summary judgment dismissing so much of the cause of action to recover damages pursuant to Labor Law § 241 (6) as was based on an alleged violation of 12 NYCRR 23-1.7 (d), and the plaintiff cross-appeals from so much of the same order as granted those branches of the defendants’ motion which were for summary judgment dismissing the cause of action to recover damages pursuant to Labor Law § 200 and so much of the cause of action to recover damages pursuant to Labor Law § 241 (6) as was based on alleged violations of 12 NYCRR 23-1.5 and 23-4.2.
Ordered that the order is affirmed insofar as appealed and cross-appealed from, without costs or disbursements.
The defendants contracted with New York Plumbing Heating & Cooling Corporation (hereinafter the contractor) to replace underground water main pipes at their Astoria facility. The
The plaintiff commenced this action to recover damages pursuant to, inter alia, Labor Law §§ 200 and 241 (6). Following joinder of issue and discovery, the defendants moved for summary judgment dismissing the complaint. The Supreme Court granted the defendants’ motion, except for that branch which was for summary judgment dismissing so much of the cause of action to recover damages pursuant to Labor Law § 241 (6) as was based on an alleged violation of 12 NYCRR 23-1.7 (d).
The Supreme Court properly denied that branch of the defendants’ motion which was for summary judgment dismissing so much of the cause of action to recover damages pursuant to Labor Law § 241 (6) as was based on an alleged violation of 12 NYCRR 23-1.7 (d). The defendants failed to establish their prima facie entitlement to judgment as a matter of law on that portion of the cause of action, as they failed to demonstrate that, under the circumstances, the tarp-covered pile of soil and dirt did not qualify as an “elevated working surface” within the meaning of 12 NYCRR 23-1.7 (d) (see Doyne v Barry, Bette & Led Duke, 246 AD2d 756 , 759 [1998]; see also Rizzuto v L.A. Wenger Contr. Co., 91 NY2d 343 , 350-351 [1998]; Hammond v International Paper Co., 178 AD2d 798 , 799 [1991]).
The Supreme Court properly granted that branch of the defendants’ motion which was for summary judgment dismissing the cause of action to recover damages pursuant to Labor Law § 200. To be held liable where, as here, the accident in question arose from the manner in which the work was being performed, it must be shown that the “party to be charged had the author
The plaintiff’s remaining contentions are without merit. Skelos, J.E, Dickerson, Belen and Lott, JJ., concur.
Cases cited
- Doyne v. Barry, Bette & Led Duke, Inc. 246 AD2d 756 at 759 p. 683
- Rizzuto v. L.A. Wenger Contracting Co. 91 NY2d 343 at 350-351 p. 683
- Hammond v. International Paper Co. 178 AD2d 798 at 799 p. 683
- Ortega v. Puccia 57 AD3d 54 at 61 p. 684
- Comes v. New York State Electric & Gas Corp. 82 NY2d 876 at 877 p. 684
- Gasques v. State 59 AD3d 666 at 668 p. 684
- Gasques v. State 15 NY3d 869 p. 684
- Russin v. Louis N. Picciano & Son 54 NY2d 311 at 317 p. 684
- McLeod v. Corporation of Presiding Bishop of Church of Jesus Christ of Latter Day Saints 41 AD3d 796 at 798 p. 684
- Peay v. New York City School Construction Authority 35 AD3d 566 at 567 p. 684
- Bink v. F.C. Queens Place Associates, LLC 27 AD3d 408 p. 684