A proceeding pursuant to CPLR article 78 seeking review of any determination of a zoning board of appeals “shall be
Here, the 30-day limitations period of Town Law § 267-c (1) commenced to run on June 10, 2010, when the minutes of the ZBA’s meeting of May 27, 2010, were filed in the office of the Town Clerk. The petitioners untimely commenced the proceeding more than 30 days later, on July 26, 2010. Contrary to the petitioners’ contention, their allegation that the ZBA made an erroneous SEQRA determination failed to establish a jurisdictional defect which tolled the limitations period (see 420 Tenants Corp. v EBM Long Beach, LLC, 41 AD3d 641 , 643 [2007]). Accordingly, the Supreme Court properly granted the respondents’ motions pursuant to CPLR 3211 (a) (5) to dismiss the proceeding as time-barred and dismissed the proceeding, with prejudice. Dillon, J.P, Angiolillo, Florio and Dickerson, JJ., concur.
Cases cited
- Save the Pine Bush, Inc. v. Zoning Board 220 AD2d 90 at 94 p. 664
- Kennedy v. Zoning Board of Appeals 78 NY2d 1083 at 1084-1085 p. 664
- Mosher v. Town of Southport Zoning Board of Appeals 5 AD3d 840 at 841 p. 664
- Casolaro v. Zoning Board of Appeals of Elmsford 200 AD2d 742 p. 664
- 420 Tenants Corp. v. EBM Long Beach, LLC 41 AD3d 641 at 643 p. 664