Majority
Appeal from an order of the Supreme Court, Erie County (Diane Y. Devlin, J.), entered January 6, 2011 in a personal injury action. The order denied defendants’ motion for summary judgment.
It is hereby ordered that the order so appealed from is unanimously modified on the law by granting those parts of defendants’ motion for summary judgment dismissing the Labor Law § 200 and common-law negligence causes of action insofar as they are based on defendants’ alleged supervision and control of plaintiff’s work and the Labor Law § 241 (6) cause of action, and dismissing those causes of action to that extent, and as modified the order is affirmed without costs.
Memorandum: Plaintiffs commenced this Labor Law and common-law negligence action seeking damages for injuries sustained by Thomas Bannister (plaintiff) when he slipped on ice and fell while working in an open courtyard at a school renovation project. We agree with defendants that Supreme Court erred in denying those parts of their motion seeking summary judgment dismissing the Labor Law § 200 and common-law negligence causes of action insofar as they are based on defendants’ alleged supervision and control over plaintiffs work, and we therefore modify the order accordingly. Defendants established as a matter of law that they did not have the authority to
We agree with defendants that the court erred in denying that part of their motion seeking summary judgment dismissing the Labor Law § 241 (6) cause of action, and we therefore further modify the order accordingly. To recover pursuant to Labor Law § 241 (6), plaintiffs “must allege a violation of an applicable regulation ‘mandating compliance with concrete specifications,’ as opposed to ‘those that establish general safety standards’ ” (Motyka v Ogden Martin Sys. of Onondaga Ltd. Partnership, 272 AD2d 980 , 981 [2000], quoting Ross v Curtis-Palmer Hydro-Elec. Co., 81 NY2d 494 , 505 [1993]). Although the complaint, as amplified by the bill of particulars, alleges multiple violations of the Industrial Code, plaintiffs conceded at oral argument on defendants’ motion that the section 241 (6) cause of action was premised solely upon a violation of 12 NYCRR 23-1.7 (d). Thus, the court erred in denying those parts of defendants’ motion seeking summary judgment dismissing the Labor Law § 241 (6) cause of action insofar as it was based on the alleged violation of the remaining regulations.
Pursuant to 12 NYCRR 23-1.7 (d), “[e]mployers shall not. . . permit any employee to use a floor, passageway, walkway, scaf
Cases cited
- Ortega v. Puccia 57 AD3d 54 at 61-63 p. 1295
- Zuckerman v. City of New York 49 NY2d 557 at 562 p. 1295
- McCormick v. 257 W. Genesee, LLC 78 AD3d 1581 at 1582 p. 1295
- Ozimek v. Holiday Valley, Inc. 83 AD3d 1414 at 1416 p. 1295
- Sullivan v. RGS Energy Group, Inc. 78 AD3d 1503 at 1503 p. 1295
- Ross v. Curtis-Palmer Hydro-Electric Co. 81 NY2d 494 at 505 p. 1295
- Bale v. Pyron Corp. 256 AD2d 1128 at 1128 p. 1296
- Ramski v. Zappia Enterprises, Inc. 229 AD2d 990 p. 1296