Majority
In an action to recover damages for continuing public nuisance, the
Ordered that the order is affirmed, with costs.
The plaintiff alleges that, pursuant to a contract with Nassau County, the defendant completed certain sewer construction work in 1986, and that defects in the construction work constitute and contribute to a continuing public nuisance. The action is time-barred for the reasons stated in the companion case of Village of Lindenhurst v J.D. Posillico, Inc. ( 94 AD3d 1101 [2012] [decided herewith]).
The plaintiffs contentions relating to alleged statutory violations are not properly before this Court. Rivera, J.P, Dillon, Angiolillo and Leventhal, JJ., concur.