Majority
In an action to recover damages for personal injuries, (1) the plaintiff appeals, as limited by her brief, from so much of an order of the Supreme Court, Queens County (Rosengarten, J.), dated August 30, 2010, as granted that branch of the motion of the defendant Howard L. Zimmerman Architect, EC., which was for summary judgment dismissing the complaint insofar as asserted against it, (2) the defendant Rochdale Village, Inc., the defendant Arcadia Architectural Froducts, Inc., and the defendants Werfel & Associates Architects, EC., Lawrence Werfel & Associates, and Lawrence Werfel separately appeal, as limited by their respective briefs, from so much of the same order as granted those branches of the motion of the defendant Howard L. Zimmerman Architect, EC., which were for summary judgment dismissing the complaint and all cross claims insofar as asserted against it, and (3) the defendant Howard L. Zimmerman Architect, EC., cross-appeals from so much of the same order as denied that branch of its motion which was for summary judgment on its cross claim for contractual indemnification against the defendant Rochdale Village, Inc.
Ordered that the appeal by the defendant Rochdale Village,
Ordered that the order is modified, on the law, (1) by deleting the provision thereof granting that branch of the motion of the defendant Howard L. Zimmerman Architect, EC., which was for summary judgment dismissing the complaint insofar as asserted against it, and substituting therefor a provision denying that branch of the motion as premature, (2) by deleting the provision thereof granting that branch of the motion of the defendant Howard L. Zimmerman Architect, EC., which was for summary judgment dismissing the cross claims for contribution insofar as asserted against it, and substituting therefor a provision denying that branch of the motion, and (3) by adding a provision thereto denying that branch of the motion of the defendant Howard L. Zimmerman Architect, EC., which was pursuant to CPLR 3211 (a) (1) and (7) to dismiss the complaint insofar as asserted against it; as so modified, the order is affirmed insofar as reviewed on the appeals and insofar as cross-appealed from; and it is further,
Ordered that one bill of costs is awarded to the defendant Rochdale Village, Inc., the defendant Arcadia Architectural Products, Inc., and the defendants Werfel & Associates Architects, EC., Lawrence Werfel & Associates, and Lawrence Werfel, appearing separately and filing separate briefs, payable by the defendant Howard L. Zimmerman Architect, EC., and one bill of costs is awarded to the plaintiff, payable by the defendant Rochdale Village, Inc., the defendant Arcadia Architectural Products, Inc., and the defendants Werfel & Associates Architects, EC., Lawrence Werfel & Associates, and Lawrence Werfel, appearing separately and filing separate briefs.
The plaintiff allegedly sustained injuries when she tripped and fell on a metal bar at the threshold of a sliding glass door leading to the terrace of her apartment. The owner of the building, the defendant Rochdale Village, Inc. (hereinafter Rochdale), had hired the defendant Howard L. Zimmerman Architect, EC. (hereinafter Zimmerman), an architectural firm, to prepare construction documents for the project during which the subject door was installed. The plaintiff commenced this action against,
Prior to answering the complaint, Zimmerman moved, inter alia, pursuant to CPLR 3211 (a) (1) and (7), or in the alternative, pursuant to CPLR 3212, to dismiss the complaint and all cross claims insofar as asserted against it. The Supreme Court granted that branch of the motion which was for summary judgment dismissing the complaint and all cross claims. In addition, it denied that branch of Zimmerman’s motion which was for summary judgment on its cross claim for contractual indemnification against Rochdale. We modify.
Although the Supreme Court was authorized to treat that branch of Zimmerman’s pre-answer motion which was pursuant to CPLR 3211 (a) (1) and (7) to dismiss the complaint insofar as asserted against it as one for summary judgment upon “adequate notice to the parties” (CPLR 3211 [c]), no such notice was given, and none of the exceptions to the notice requirement is applicable (see Mihlovan v Grozavu, 72 NY2d 506 [1988]; Bowes v Healy, 40 AD3d 566 , 566-567 [2007]). Contrary to Zimmerman’s contention, “the unilateral actions of a party in seeking summary judgment on a CPLR 3211 (a) (7) motion cannot constitute ‘adequate notice’ to the other party in compliance with the requirement of CPLR 3211 (c)” (Mihlovan v Grozavu, 72 NY2d at 508 n; see Wiesen v New York Univ., 304 AD2d 459 , 460 [2003]). Moreover, the motion did not exclusively involve “a purely legal question rather than any issues of fact” (Mihlovan v Grozavu, 72 NY2d at 508 ; see Bowes v Healy, 40 AD3d at 567 ), and the record does not establish that the plaintiff was “laying bare [her] proof and deliberately charting a summary judgment course” (Four Seasons Hotels v Vinnik, 127 AD2d 310 , 320 [1987]; cf. McNamee Constr. Corp. v City of New Rochelle, 29 AD3d 544 , 545 [2006]). Thus, that branch of Zimmerman’s motion which was for summary judgment dismissing the complaint insofar as asserted against it must be denied as premature (see City of Rochester v Chiarella, 65 NY2d 92 , 101-102 [1985]), and this Court will apply the standards applicable to a motion to dismiss pursuant to CPLR 3211 (a) in determining whether Zimmerman was entitled to dismissal of the complaint insofar as asserted against it (see Bokara Rug Co., Inc. v Kapoor, 93 AD3d 583 [2012]; Velez v Captain Luna's Mar., 74 AD3d 1191 , 1191-1192 [2010]).
When a party moves to dismiss a complaint pursuant to CPLR 3211 (a) (7), “the standard is whether the pleading states a cause of action,” and, in considering such a motion, “the court must accept the facts as alleged in the complaint as true, accord plaintiffs the benefit of every possible favorable inference, and determine only whether the facts as alleged fit within any cognizable legal theory” (Sokol v Leader, 74 AD3d 1180 , 1180-1181 [2010] [internal quotation marks omitted]; see Leon v Martinez, 84 NY2d 83 , 87-88 [1994]). When the moving party submits evidentiary material in support of his or her motion, “the criterion then becomes ‘whether the proponent of the pleading has a cause of action, not whether he [or she] has stated one’ ” (Sokol v Leader, 74 AD3d at 1181-1182 , quoting Guggenheimer v Ginzburg, 43 NY2d 268 , 275 [1977]). However, “a motion to dismiss pursuant to CPLR 3211 (a) (7) must be denied ‘unless it has been shown that a material fact as claimed by the pleader to be one is not a fact at all and unless it can be said that no significant dispute exists regarding it’ ” (Sokol v Leader, 74 AD3d at 1182 , quoting Guggenheimer v Ginzburg, 43 NY2d at 275 ). Here, dismissal pursuant to CPLR 3211 (a) (7) was not warranted, since Zimmerman’s evidentiary materials did not establish that a material fact alleged in the complaint “was, undisputedly, ‘not a fact at all’ ” (Sokol v Leader, 74 AD3d at 1182 , quoting Guggenheimer v Ginzburg, 43 NY2d 268 , 275 [1977]; see Ascani v El Du Pont De Nemours & Co., 85 AD3d 830 , 830 [2011]). Accordingly, those branches of Zimmerman’s motion which were pursuant to CPLR 3211 (a) (1) and (7) to
Contrary to Rochdale’s contention, those branches of Zimmerman’s motion which were for summary judgment dismissing the cross claims insofar as asserted against it, and for summary judgment on its cross claim for contractual indemnification against Rochdale, were “not premature simply because a formal answer thereto was never interposed,” as the cross claims did not demand an answer (Aetna Cas. & Sur. Co. v McCarthy, 246 AD2d 406 , 406-407 [1998]; see CPLR 3011).
The Supreme Court improperly granted that branch of Zimmerman’s motion which was for summary judgment dismissing the cross claims of Rochdale, Arcadia, and Werfel seeking contribution from Zimmerman. Contrary to Zimmerman’s contention, it failed to eliminate all triable issues of fact as to whether it negligently designed the doorway threshold upon which the plaintiff tripped (see Torres v W.J. Woodward Constr., Inc., 32 AD3d 847 , 848 [2006]; see generally Cubito v Kreisberg, 69 AD2d 738 , 744-745 [1979], affd 51 NY2d 900 [1980]; cf. Gonzalez v Clay, 83 AD3d 999 , 999 [2011]). Since Zimmerman failed to meet its prima facie burden, it is unnecessary to consider whether the opposition papers were sufficient to raise a triable issue of fact (see Winegrad v New York Univ. Med. Ctr., 64 NY2d 851 , 853 [1985]).
However, the Supreme Court properly granted those branches of Zimmerman’s motion which were for summary judgment dismissing the cross claims asserted against it seeking common-law and contractual indemnification and sounding in breach of contract for failure to procure insurance, breach of warranty, and strict products liability. Zimmerman established its prima facie entitlement to judgment as a matter of law dismissing the cross claims asserted against it seeking contractual indemnification and sounding in breach of contract for failure to procure insurance by demonstrating that it did not have a contractual relationship with Arcadia, and that its contract with Rochdale did not require it to indemnify Rochdale or to procure insurance naming Rochdale as an additional insured (see Galvin Bros., Inc. v Town of Babylon, N.Y., 91 AD3d 715 , 716 [2012]; Richards v Passarelli, 77 AD3d 905 , 908-910 [2010]). Zimmerman also established its prima facie entitlement to judgment as a matter of law dismissing the cross claims asserted against it sounding in breach of warranty and strict products liability by demonstrating that the contract between Rochdale and Zimmerman was for the performance of services (see Mallards Dairy, LLC v E&M Engrs. & Surveyors, P.C., 71 AD3d 1415 ,
Contrary to Zimmerman’s contention, it was not entitled to summary judgment on its cross claim for contractual indemnification against Rochdale. Zimmerman improperly asserted the cross claim in a separate pleading prior to answering the complaint (see CPLR 3011). In any event, summary judgment on the cross claim would have been premature, since Zimmerman failed to establish, as a matter of law, that the plaintiff’s claim did not result from Zimmerman’s negligence in the performance of its services, as required by the “third-party claim” indemnification clause of its contract with Rochdale (see Bryde v CVS Pharmacy, 61 AD3d 907 , 908 [2009]; cf. Pritchard v Sub-urban Carting Corp., 90 AD3d 729 , 731 [2011]). Accordingly, that branch of Zimmerman’s motion which was for summary judgment on its contractual indemnification cross claim against Rochdale was properly denied.
The parties’ remaining contentions either need not be reached in light of our determination, are not properly before this Court, or are without merit. Florio, J.P., Balkin, Chambers and Cohen, JJ., concur.
Cases cited
- Mihlovan v. Grozavu 72 NY2d 506 p. 1016
- Bowes v. Healy 40 AD3d 566 at 566-567 p. 1016
- Wiesen v. New York University 304 AD2d 459 at 460 p. 1016
- Four Seasons Hotels Ltd. v. Vinnik 127 AD2d 310 at 320 p. 1016
- McNamee Construction Corp. v. City of New Rochelle 29 AD3d 544 at 545 p. 1016
- Velez v. Captain Luna's Marina 74 AD3d 1191 at 1191-1192 p. 1016
- Integrated Construction Services, Inc. v. Scottsdale Insurance 82 AD3d 1160 at 1162-1163 p. 1017
- Granada Condominium III Ass'n v. Palomino 78 AD3d 996 at 996 p. 1017
- Fontanetta v. John Doe 1 73 AD3d 78 at 84-86 p. 1017
- Suchmacher v. Manana Grocery 73 AD3d 1017 at 1017 p. 1017
- Sokol v. Leader 74 AD3d 1180 at 1180-1181 p. 1017
- Leon v. Martinez 84 NY2d 83 at 87-88 p. 1017
- Guggenheimer v. Ginzburg 43 NY2d 268 at 275 p. 1017
- Ascani v. EI Du Pont De Nemours & Co. 85 AD3d 830 at 830 p. 1017
- Torres v. W.J. Woodward Construction, Inc. 32 AD3d 847 at 848 p. 1018
- Cubito v. Kreisberg 69 AD2d 738 at 744-745 p. 1018
- Cubito v. Kreisberg 51 NY2d 900 p. 1018
- Gonzalez v. Clay 83 AD3d 999 at 999 p. 1018
- Winegrad v. New York University Medical Center 64 NY2d 851 at 853 p. 1018
- Galvin Bros. v. Town of Babylon 91 AD3d 715 at 716 p. 1018
- Richards v. Passarelli 77 AD3d 905 at 908-910 p. 1018
- Mallards Dairy, LLC v. E&M Engineers & Surveyors, P.C. 71 AD3d 1415 p. 1018
- Trustees of Columbia University v. Siegel 192 AD2d 151 at 155 p. 1019
- Corley v. Country Squire Apartments, Inc. 32 AD3d 978 at 979 p. 1019
- Bryde v. CVS Pharmacy 61 AD3d 907 at 908 p. 1019